Requests shown9,1872,001.0 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9,187 requests · page 106 of 184
ProjectCapacityStatusLocationRegionQueuedOnline
Magley Solar Energy Center
Solar
135 MWAgreement signed Adams, INPJM Sep 2020target 2029
Solar project J3283, Grand Traverse County
Solar
135 MWIn study Grand Traverse, MIMISO Apr 2024target 2028
Solar + storage project J3082, Franklin Parish County
Solar + storage
135 MWIn study Franklin Parish, LAMISO Sep 2022target 2026
Solar project J2985, Chicot County
Solar
135 MWIn study Chicot, ARMISO Sep 2022target 2025
White Creek Solar
Solar · White Creek Solar, LLC
135 MWIn study Livingston, NYNYISO Nov 2018target 2028
Stonewall BESS
Solar + storage · Stonewall ESS, LLC
135 MWIn study Stonewall, TXERCOT Feb 2025target 2028
Solar project J1125, Cross County
Solar
135 MWUnder construction Cross, ARMISO Mar 2018target 2023
Surplus; J33/J734
Other
135 MWIn study Ford, ILMISO May 2023target 2026
Surplus; J734
Other
135 MWIn study Mclean, ILMISO Dec 2022target 2026
Fraser Energy Storage
Battery storage · EDF Renewables Development, Inc.
135 MWIn study Delaware, NYNYISO Aug 2024target 2029
SR Warthen
Solar
135 MWIn study Washington, GASoutheast Dec 2024target 2029
Solar + storage project J2648, Champaign County
Solar + storage
135 MWIn study Champaign, ILMISO Sep 2022target 2027
Solar project GEN-2022-007, Lyon County
Solar
135 MWIn study Lyon, KSSPP May 2022target 2028
Solar project J2287, Bolivar County
Solar
135 MWIn study Bolivar, MSMISO Sep 2021target 2024
Solar project J1520, Worth County
Solar
135 MWUnder construction Worth, IAMISO Jun 2020target 2027
Gas project H037, Lucas County
Gas
135 MWAgreement signed Lucas, OHMISO May 2008target 2010
Marathon BESS
Battery storage · Marathon Power
135 MWIn study Suffolk, NYNYISO Sep 2024target 2028
Onshore wind project J1842, Cross County
Onshore wind
135 MWIn study Cross, ARMISO Oct 2021target 2024
Battery storage project GEN-2023-SR7, Wayne County
Battery storage
135 MWIn study Wayne, NESPP Dec 20222024
Onshore wind project AI2-390, Mclean County
Onshore wind
134 MWIn study Mclean, ILPJM Mar 2023target 2027
Pham BESS
Battery storage · ASB1, LLC
133 MWIn study Anderson, TXERCOT Jun 2024target 2028
Giga Texas Data Center
Battery storage · Giga Texas Energy, LLC
133 MWAgreement signed Travis, TXERCOT Aug 2024target 2025
Millers Branch Solar III
Solar · Miller's Branch Solar LLC
133 MWAgreement signed Haskell, TXERCOT Aug 2024target 2026
Solar project J2809, Iroquois County
Solar
133 MWIn study Iroquois, ILMISO Sep 2022target 2026
Halcon Storage
Battery storage · TX BESS A LLC
133 MWIn study Starr, TXERCOT May 2023target 2028
Double A Solar SLF
Solar + storage · Double A Solar, LLC
133 MWIn study Goliad, TXERCOT Jun 2024target 2027
Gas project J3936, Kenosha County
Gas
132 MWIn study Kenosha, WIMISO Feb 2025target 2027
Surplus; J1316
Gas
132 MWIn study Kenosha, WIMISO Jan 2025target 2026
Alta Vista Suntower Generating Station
Solar + storage
132 MWAgreement signed Los Angeles, CACAISO Jan 20082013
Solar project J1918, Montcalm County
Solar
132 MWIn study Montcalm, MIMISO Aug 2021target 2026
Solar project J3724, Vigo County
Solar
132 MWIn study Vigo, INMISO Apr 2024target 2028
Wind + storage project 614, Twin Falls County
Wind + storage · Magic Valley Energy, LLC
132 MWPaused / redesign Twin Falls, IDWest Aug 2021target 2026
Montezuma II
Wind + storage
132 MWAgreement signed Solano, CACAISO May 20072012
Gas project 118, Polk County
Gas
132 MWIn study Polk, FLSoutheast Apr 2025target 2026
Kodiak AGR1
Other · Hunt Energy Network, LLC
132 MWIn study Reeves, TXERCOT Feb 2024target 2027
Battery storage project GEN-2026-PR4, Hansford County
Battery storage
132 MWIn study Hansford, TXSPP Dec 2025
Solar project AG2-152, Pittsylvania County
Solar · Virginia Electric and Power Company
131 MWIn study Pittsylvania, VAPJM Mar 2025target 2024
Onshore wind project G0992, Skagit County
Onshore wind
131 MWIn study Skagit, WAWest Nov 2023target 2028
Maratua Solar
Solar · BDPU Solar Maratua, LLC
131 MWIn study Grimes, TXERCOT Oct 2025target 2028
Pecan Prairie South
Solar · ConnectGen Operating LLC
131 MWIn study Leon, TXERCOT Aug 2019target 2027
Starlight Solar
Solar + storage · Mills Tx Solar LLC
131 MWIn study Mills, TXERCOT Feb 2024target 2027
Anagram Solar
Solar · Anagram Solar
131 MWIn study Live Oak, TXERCOT Apr 2024target 2026
White Wing Storage
Solar + storage · White Wing Solar, LLC
130 MWIn study Wilbarger, TXERCOT Aug 2025target 2028
Solar + storage project G0691, Benton County
Solar + storage
130 MWIn study Benton, WAWest Sep 2021target 2023
Solar project J2885, Red Lake County
Solar
130 MWIn study Red Lake, MNMISO Sep 2022target 2025
Solar + storage project 654, Bingham County
Solar + storage · Pingree Solar LLC
130 MWPaused / redesign Bingham, IDWest May 2022target 2028
Solar + storage project IC-966, Decatur County
Solar + storage
130 MWAgreement signed Decatur, GASoutheast Jun 2021target 2024
Solar + storage project 773, Ada County
Solar + storage
130 MWIn study Ada, IDWest Apr 2025target 2030
Battery storage project 24-03011, Larimer County
Battery storage
130 MWIn study Larimer, COWest Mar 2024target 2027
LA130S Project
Solar + storage
130 MWIn study Luna, NMWest Mar 2019target 2026
Page 106 of 184

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)