SOLAR · SPPSolar project GEN-2022-007, Lyon County
Solar project GEN-2022-007, Lyon County is a 135 MW solar request in interconnection study in the SPP interconnection queue, in Lyon County, Kansas, connecting to WERE.
Queue statusIn planning
- PlanningQueued May 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GEN-2022-007
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- WERE
- Connection point (POI)
- Lang - Reading 115 kV Transmission Line
- Location
- Lyon County, Kansas
- Technology
- Solar: 135 MW
- Total requested
- 135 MW
- Service type
- NRIS and ERIS
- Study phase
- FACILITY STUDY STAGE
- Queue status
- Active
- Entered queue
- 26 May 2022
- Proposed online date
- December 2028
Location
Marker shows the centre of Lyon County; the queue data does not give exact sites.
Other requests in Lyon County
- Gas project GEN-2006-027, Lyon CountyGas · 380 MW · built
- Gas project GEN-2006-028, Lyon CountyGas · 360 MW · built
- Onshore wind project GEN-2015-073, Lyon CountyOnshore wind · 200 MW · built
- Gas project GEN-2015-051, Lyon CountyGas · 916 MW · withdrawn
- Gas project GEN-2015-050, Lyon CountyGas · 464 MW · withdrawn
- Onshore wind project GEN-2009-005, Lyon CountyOnshore wind · 200 MW · withdrawn
- Solar project GEN-2024-358, Lyon CountySolar · 145 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem