Solar project GEN-2022-007, Lyon County

Solar project GEN-2022-007, Lyon County is a 135 MW solar request in interconnection study in the SPP interconnection queue, in Lyon County, Kansas, connecting to WERE.

Queue statusIn planning
  1. PlanningQueued May 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2022-007
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WERE
Connection point (POI)
Lang - Reading 115 kV Transmission Line
Location
Lyon County, Kansas
Technology
Solar: 135 MW
Total requested
135 MW
Service type
NRIS and ERIS
Study phase
FACILITY STUDY STAGE
Queue status
Active
Entered queue
26 May 2022
Proposed online date
December 2028

Location

Marker shows the centre of Lyon County; the queue data does not give exact sites.

Power plants in Kansas · Transmission lines in Kansas

Other requests in Lyon County