๐Ÿ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more โ†’ Skip to main content

United States โ€บ Grid โ€บ Interconnection queues โ€บ Kansas

OCTARY USA ยท INTERCONNECTION QUEUES

Interconnection queue in Kansas

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown14032.6 GW
Active in queue32.6 GW140 requests
Agreement signed9,162 MW47 requests
Withdrawn38780.4 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

140 requests ยท page 1 of 3
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project GEN-2024-129, Labette County
Gas
910 MWIn study Labette, KSSPP Mar 2025target 2030
Gas project GEN-2024-249, Pottawatomie County
Gas
721 MWIn study Pottawatomie, KSSPP Mar 2025target 2032
Gas project ERAS-2025-008, Sumner County
Gas
721 MWIn study Sumner, KSSPP Sep 2025target 2029
Gas project ERAS-2025-006, Reno County
Gas
718 MWIn study Reno, KSSPP Sep 2025target 2030
Solar + storage project GEN-2020-007, Linn County
Solar + storage
650 MWAgreement signed Linn, KSSPP Apr 2020target 2028
Gas project ERAS-2025-017, Finney County
Gas
600 MWIn study Finney, KSSPP Sep 2025target 2029
Solar project GEN-2021-030, Linn County
Solar
510 MWIn study Linn, KSSPP May 2021target 2026
Onshore wind project GEN-2021-070, Hodgeman County
Onshore wind
504 MWIn study Hodgeman, KSSPP Apr 2021target 2027
Solar project GEN-2017-195, Johnson County
Solar
500 MWAgreement signed Johnson, KSSPP Nov 2017target 2030
Solar project GEN-2021-096, Coffey County
Solar
500 MWIn study Coffey, KSSPP Apr 2021target 2027
Battery storage project GEN-2020-057, Finney County
Battery storage
425 MWAgreement signed Finney, KSSPP Apr 2020target 2030
Solar project GEN-2020-058, Finney County
Solar
425 MWAgreement signed Finney, KSSPP Apr 2020target 2028
Onshore wind project GEN-2024-102, Finney County
Onshore wind
401 MWIn study Finney, KSSPP Mar 2025target 2031
Onshore wind project GEN-2017-183, Hodgeman County
Onshore wind
400 MWAgreement signed Hodgeman, KSSPP Nov 2017target 2029
Solar project GEN-2024-125, Elk County
Solar
400 MWIn study Elk, KSSPP Mar 2025target 2028
Solar project GEN-2024-136, Scott County
Solar
400 MWIn study Scott, KSSPP Mar 2025target 2029
Solar + storage project ERAS-2025-015, Finney County
Solar + storage
400 MWIn study Finney, KSSPP Sep 2025target 2029
Solar project GEN-2017-184, Hodgeman County
Solar
400 MWAgreement signed Hodgeman, KSSPP Nov 2017target 2029
Solar project GEN-2024-067, Cloud County
Solar
380 MWIn study Cloud, KSSPP Oct 2024target 2029
Onshore wind project GEN-2022-161, Butler County
Onshore wind
360 MWIn study Butler, KSSPP Feb 2023target 2029
Battery storage project GEN-2021-005, Saline County
Battery storage
350 MWAgreement signed Saline, KSSPP May 2021target 2030
Solar project GEN-2023-015, Finney County
Solar
330 MWIn study Finney, KSSPP Oct 2023target 2026
Solar project GEN-2021-023, Grant County
Solar
306 MWAgreement signed Grant, KSSPP May 2021target 2030
Onshore wind project GEN-2016-111, Mcpherson County
Onshore wind
302 MWAgreement signed Mcpherson, KSSPP Nov 2016target 2027
Onshore wind project GEN-2024-258, Allen County
Onshore wind
300 MWIn study Allen, KSSPP Mar 2025target 2030
Onshore wind project GEN-2024-137, Scott County
Onshore wind
300 MWIn study Scott, KSSPP Mar 2025target 2030
Solar + storage project GEN-2024-215, Cloud County
Solar + storage
300 MWIn study Cloud, KSSPP Mar 2025target 2029
Solar project GEN-2023-099, Jackson County
Solar
300 MWIn study Jackson, KSSPP Oct 2023target 2030
Solar project GEN-2022-013, Bourbon County
Solar
300 MWIn study Bourbon, KSSPP Jun 2022target 2028
Onshore wind project GEN-2024-138, Scott County
Onshore wind
300 MWIn study Scott, KSSPP Mar 2025target 2030
Onshore wind project GEN-2024-142, Mcpherson County
Onshore wind
300 MWIn study Mcpherson, KSSPP Mar 2025target 2031
Gas project GEN-2024-253, Leavenworth County
Gas
300 MWIn study Leavenworth, KSSPP Mar 2025target 2027
Onshore wind project GEN-2021-056, Harper County
Onshore wind
300 MWAgreement signed Harper, KSSPP Apr 2021target 2030
Battery storage project GEN-2024-339, Leavenworth County
Battery storage
300 MWIn study Leavenworth, KSSPP Mar 2025target 2029
Onshore wind project GEN-2024-016, Smith County
Onshore wind
300 MWIn study Smith, KSSPP Oct 2024target 2028
Onshore wind project GEN-2023-107, Finney County
Onshore wind
300 MWIn study Finney, KSSPP Oct 2023target 2030
Battery storage project GEN-2025-SR16, Sumner County
Battery storage
300 MWIn study Sumner, KSSPP Jun 2025target 2026
Onshore wind project GEN-2024-144, Scott County
Onshore wind
300 MWIn study Scott, KSSPP Mar 2025target 2030
Battery storage project GEN-2021-006, Labette County
Battery storage
300 MWIn study Labette, KSSPP May 2021target 2026
Solar + storage project GEN-2024-166, Sedgwick County
Solar + storage
275 MWIn study Sedgwick, KSSPP Mar 2025target 2030
Solar project GEN-2022-015, Decatur County
Solar
270 MWIn study Decatur, KSSPP Jun 2022target 2028
Onshore wind project GEN-2017-120, Dickinson County
Onshore wind
260 MWAgreement signed Dickinson, KSSPP Nov 2017target 2028
Battery storage project GEN-2021-029, Linn County
Battery storage
254 MWIn study Linn, KSSPP May 2021target 2026
Onshore wind project GEN-2019-030, Ford County
Onshore wind
252 MWAgreement signed Ford, KSSPP Apr 2019target 2027
Solar + storage project GEN-2020-008, Stevens County
Solar + storage
250 MWAgreement signed Stevens, KSSPP Apr 2020target 2028
Solar project GEN-2023-220, Osage County
Solar
250 MWIn study Osage, KSSPP Oct 2023target 2029
Solar project GEN-2023-221, Osage County
Solar
250 MWIn study Osage, KSSPP Oct 2023target 2029
Solar project GEN-2024-032, Stevens County
Solar
250 MWIn study Stevens, KSSPP Oct 2024target 2028
Solar project GEN-2024-139, Coffey County
Solar
250 MWIn study Coffey, KSSPP Mar 2025target 2033
Battery storage project GEN-2024-176, Reno County
Battery storage
250 MWIn study Reno, KSSPP Mar 2025target 2028
Page 1 of 3

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)