United States โ€บ Grid โ€บ Interconnection queues โ€บ Nevada

OCTARY USA ยท INTERCONNECTION QUEUES

Interconnection queue in Nevada

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24981.5 GW
Active in queue81.5 GW249 requests
Agreement signed20.9 GW82 requests
Withdrawn35588.4 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

249 requests ยท page 1 of 5
ProjectCapacityStatusLocationRegionQueuedOnline
Arida 2 Solar Farm
Solar + storage
1,400 MWIn study Clark, NVCAISO Apr 2019target 2029
Mosey
Solar + storage
1,081 MWAgreement signed Clark, NVCAISO Apr 2021target 2029
Water Rock Solar 2
Solar + storage
1,034 MWIn study Nye, NVCAISO Apr 2021target 2028
Silver Star Solar
Solar + storage
1,034 MWAgreement signed Nye, NVCAISO Apr 2021target 2028
Rock Valley Energy Center
Solar + storage
1,024 MWAgreement signed Nye, NVCAISO Apr 2021target 2029
Solar + storage project 25-00394, Esmerelda County
Solar + storage
1,000 MWIn study Esmerelda, NVWest Jul 2025target 2028
Solar + storage project Company 238, Nye County
Solar + storage
1,000 MWIn study Nye, NVWest Jan 2023target 2028
Gas project 25-00427, Storey County
Gas
1,000 MWIn study Storey, NVWest Jul 2025target 2028
Solar + storage project Q88, Clark County
Solar + storage
1,000 MWIn study Clark, NVWest Apr 2022target 2028
Bristlecone
Solar + storage
921 MWIn study Nye, NVCAISO Apr 2023target 2030
Arida 3 Solar Farm
Solar + storage
900 MWIn study Clark, NVCAISO Apr 2020target 2030
Solar + storage project 25-00432, Lyon County
Solar + storage
900 MWIn study Lyon, NVWest Jul 2025target 2029
Purple Sage Energy Center
Solar + storage
817 MWAgreement signed Clark, NVCAISO Apr 2020target 2028
Battery storage project Company 257, Clark County
Battery storage
800 MWIn study Clark, NVWest Sep 2023target 2026
Other project Company KD, White Pine County
Other
750 MWPaused / redesign White Pine, NVWest Sep 2019target 2026
Arida Solar Farm
Solar + storage
740 MWIn study Clark, NVCAISO Apr 2018target 2027
Solar + storage project Company LU, Mineral County
Solar + storage
700 MWAgreement signed Mineral, NVWest Sep 2021target 2029
Solar + storage project Company MI, Churchill County
Solar + storage
700 MWAgreement signed Churchill, NVWest Sep 2021target 2024
Kawich
Solar + storage
700 MWAgreement signed Clark, NVCAISO Apr 2021target 2029
Bonanza Peak Solar Farm
Solar + storage
641 MWAgreement signed Clark, NVCAISO Apr 2019target 2027
Larrea Solar
Solar + storage
614 MWIn study Clark, NVCAISO Apr 2021target 2028
Solar + storage project Company 201, Clark County
Solar + storage
600 MWPaused / redesign Clark, NVWest Sep 2021target 2029
Bonanza Solar
Solar + storage
600 MWAgreement signed Clark, NVCAISO Apr 2019target 2028
Gas project 25-00419, Washoe County
Gas
600 MWIn study Washoe, NVWest Jul 2025target 2028
Solar + storage project Company 200, Clark County
Solar + storage
600 MWPaused / redesign Clark, NVWest Sep 2021target 2029
Gas project 25-00428, Lincoln County
Gas
600 MWIn study Lincoln, NVWest Jul 2025target 2028
Geothermal project 25-00412, Humboldt County
Geothermal
600 MWIn study Humboldt, NVWest Jul 2025target 2032
Other project Company KR, White Pine County
Other
600 MWAgreement signed White Pine, NVWest Sep 2020target 2028
Solar + storage project Company NU, White Pine County
Solar + storage
600 MWPaused / redesign White Pine, NVWest Sep 2022target 2029
Solar + storage project Company 254, Nye County
Solar + storage
600 MWIn study Nye, NVWest Sep 2023target 2026
Solar + storage project Company NX, White Pine County
Solar + storage
600 MWPaused / redesign White Pine, NVWest Sep 2022target 2025
Solar + storage project Company OT, Lander County
Solar + storage
600 MWPaused / redesign Lander, NVWest Jan 2023target 2027
Solar + storage project 25-00395, Washoe County
Solar + storage
600 MWIn study Washoe, NVWest Jul 2025target 2028
Solar + storage project Company NW, White Pine County
Solar + storage
600 MWPaused / redesign White Pine, NVWest Sep 2022target 2025
Solar + storage project Company 255, Nye County
Solar + storage
600 MWIn study Nye, NVWest Sep 2023target 2027
Solar + storage project Company NQ, White Pine County
Solar + storage
600 MWPaused / redesign White Pine, NVWest Aug 2022target 2025
Solar + storage project Company NV, Humboldt County
Solar + storage
600 MWPaused / redesign Humboldt, NVWest Sep 2022target 2030
Solar + storage project 25-00416, Humboldt County
Solar + storage
600 MWIn study Humboldt, NVWest Jul 2025target 2028
Wind + storage project Company LV, White Pine County
Wind + storage
600 MWPaused / redesign White Pine, NVWest Sep 2021target 2025
Solar + storage project Company NC, Washoe County
Solar + storage
600 MWPaused / redesign Washoe, NVWest Mar 2022target 2030
Geothermal project 25-00406, Churchill County
Geothermal
600 MWIn study Churchill, NVWest Jul 2025target 2029
Gas project 25-00422, Lincoln County
Gas
600 MWIn study Lincoln, NVWest Jul 2025target 2028
Solar + storage project Company 224, Clark County
Solar + storage
600 MWPaused / redesign Clark, NVWest Aug 2022target 2030
Geothermal project 25-00409, Churchill County
Geothermal
600 MWIn study Churchill, NVWest Jul 2025target 2033
Gas project 25-00430, Storey County
Gas
570 MWIn study Storey, NVWest Jul 2025target 2030
Solar + storage project Company LW, Mineral County
Solar + storage
550 MWPaused / redesign Mineral, NVWest Sep 2021target 2029
Battery storage project Company MV, White Pine County
Battery storage
550 MWPaused / redesign White Pine, NVWest Mar 2022target 2030
Yellow Pine 3
Solar + storage
517 MWAgreement signed Clark, NVCAISO Apr 2019target 2026
Sterling
Solar + storage
500 MWIn study Clark, NVCAISO Apr 2021target 2031
Solar + storage project 25-00401, Lyon County
Solar + storage
500 MWIn study Lyon, NVWest Jul 2025target 2028
Page 1 of 5

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)