Arida Solar Farm

Arida Solar Farm is a 740 MW solar + storage request in interconnection study in the CAISO interconnection queue, in Clark County, Nevada, connecting to SCE.

Queue statusIn planning
  1. PlanningQueued Apr 2018 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
1522
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Mohave Substation 500kV
Location
Clark County, Nevada
Technology
Solar: 370 MW · Battery: 370 MW
Total requested
740 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Active
Entered queue
16 April 2018
Proposed online date
September 2027

Location

Marker shows the centre of Clark County; the queue data does not give exact sites.

Power plants in Nevada · Transmission lines in Nevada

Other requests in Clark County