Yellow Pine 3

Yellow Pine 3 is a 517 MW solar + storage request with a signed interconnection agreement in the CAISO interconnection queue, in Clark County, Nevada, connecting to GLW.

Queue statusConsented
  1. PlanningQueued Apr 2019 (completed)
  2. ConsentedMar 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
1654
Grid region
CAISO (California)
Utility / transmission owner
GLW
Connection point (POI)
Trout Canyon Substation 230 kV
Location
Clark County, Nevada
Technology
Solar: 262 MW · Battery: 255 MW
Total requested
517 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Active
Entered queue
15 April 2019
Agreement signed
1 March 2023
Proposed online date
December 2026

Location

Marker shows the centre of Clark County; the queue data does not give exact sites.

Power plants in Nevada · Transmission lines in Nevada

Other requests in Clark County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem