Battery storage project Company 242, Clark County

Battery storage project Company 242, Clark County is a 350 MW battery storage request with a signed interconnection agreement in the West interconnection queue, in Clark County, Nevada, connecting to NV Energy.

Queue statusConsented
  1. PlanningQueued Mar 2023 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
Company 242
Grid region
West (non-ISO utilities)
Utility / transmission owner
NV Energy
Location
Clark County, Nevada
Technology
Battery: 350 MW
Total requested
350 MW
Service type
Network resource (NRIS)
Study phase
IA Executed
Queue status
Active
Entered queue
13 March 2023
Proposed online date
November 2028

Location

Marker shows the centre of Clark County; the queue data does not give exact sites.

Power plants in Nevada · Transmission lines in Nevada

Other requests in Clark County