🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Nevada

SOLAR + STORAGE · CAISO

Purple Sage Energy Center

Purple Sage Energy Center is a 817 MW solar + storage request with a signed interconnection agreement in the CAISO interconnection queue, in Clark County, Nevada, connecting to GLW.

Queue statusConsented
  1. PlanningQueued Apr 2020 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget May 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
1800
Grid region
CAISO (California)
Utility / transmission owner
GLW
Connection point (POI)
Trout Canyon Substation 230 kV
Location
Clark County, Nevada
Technology
Solar: 409 MW · Battery: 408 MW
Total requested
817 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Active
Entered queue
15 April 2020
Proposed online date
May 2028

Location

Marker shows the centre of Clark County; the queue data does not give exact sites.

Power plants in Nevada · Transmission lines in Nevada

Other requests in Clark County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem