United States โ€บ Grid โ€บ Interconnection queues โ€บ Oregon

OCTARY USA ยท INTERCONNECTION QUEUES

Interconnection queue in Oregon

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown323112.5 GW
Active in queue112.5 GW323 requests
Agreement signed4,685 MW36 requests
Withdrawn1,014179.9 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

323 requests ยท page 1 of 7
ProjectCapacityStatusLocationRegionQueuedOnline
Other project G0695, Crook County
Other
3,600 MWIn study Crook, ORWest Sep 2021target 2028
Solar + storage project G1052, Deschutes County
Solar + storage
2,600 MWIn study Deschutes, ORWest Nov 2023target 2030
Solar + storage project G1051, Deschutes County
Solar + storage
2,600 MWIn study Deschutes, ORWest Nov 2023target 2030
Solar + storage project G0681, Wasco County
Solar + storage
2,000 MWIn study Wasco, ORWest Jul 2021target 2026
Solar + storage project G0699, Crook County
Solar + storage
1,800 MWIn study Crook, ORWest Sep 2021target 2025
Other project G0675, Crook County
Other
1,800 MWIn study Crook, ORWest Mar 2021target 2029
Solar + storage project G0648, Klamath County
Solar + storage
1,400 MWIn study Klamath, ORWest May 2020target 2026
Solar + storage project G0758, Jefferson County
Solar + storage
1,365 MWIn study Jefferson, ORWest Jun 2022target 2025
Other project G0864, Sherman County
Other
1,304 MWIn study Sherman, ORWest May 2023target 2027
Solar + storage project G0777, Umatilla County
Solar + storage
1,300 MWIn study Umatilla, ORWest Aug 2022target 2027
Battery storage project G1053, Crook County
Battery storage
1,300 MWIn study Crook, ORWest Nov 2023target 2031
Battery storage project G1055, Wasco County
Battery storage
1,300 MWIn study Wasco, ORWest Nov 2023target 2032
Battery storage project G1054, Crook County
Battery storage
1,300 MWIn study Crook, ORWest Nov 2023target 2031
Solar + storage project G0795, Sherman County
Solar + storage
1,300 MWIn study Sherman, ORWest Aug 2022target 2028
Solar + storage project G1050, Deschutes County
Solar + storage
1,300 MWIn study Deschutes, ORWest Nov 2023target 2028
Solar + storage project G0773, Wasco County
Solar + storage
1,300 MWIn study Wasco, ORWest Aug 2022target 2028
Solar + storage project G0797, Wasco County
Solar + storage
1,300 MWIn study Wasco, ORWest Aug 2022target 2028
Solar + storage project G0791, Sherman County
Solar + storage
1,300 MWIn study Sherman, ORWest Aug 2022target 2028
Solar + storage project T2-082, Klamath County
Solar + storage
1,280 MWIn study Klamath, ORWest Sep 2025target 2031
Solar + storage project T2-081, Harney County
Solar + storage
1,280 MWIn study Harney, ORWest Sep 2025target 2031
Solar project G0678, Morrow County
Solar
1,200 MWIn study Morrow, ORWest Jun 2021target 2024
Solar + storage project G0615, Sherman County
Solar + storage
1,200 MWIn study Sherman, ORWest Feb 2019target 2021
Other project G0787, Wasco County
Other
1,200 MWIn study Wasco, ORWest Aug 2022target 2028
Solar + storage project G0702, Crook County
Solar + storage
1,200 MWIn study Crook, ORWest Sep 2021target 2025
Gas project G0501, Klamath County
Gas
1,100 MWIn study Klamath, ORWest Oct 2014target 2018
Solar + storage project G0657, Klamath County
Solar + storage
1,000 MWIn study Klamath, ORWest Sep 2020target 2027
Solar project G0687, Sherman County
Solar
900 MWIn study Sherman, ORWest Aug 2021target 2024
Solar + storage project G0825, Sherman County
Solar + storage
800 MWIn study Sherman, ORWest Nov 2022target 2027
Solar + storage project G0850, Sherman County
Solar + storage
800 MWIn study Sherman, ORWest Mar 2023target 2027
Solar + storage project G0849, Sherman County
Solar + storage
800 MWIn study Sherman, ORWest Mar 2023target 2027
Solar + storage project 23-233, Jefferson County
Solar + storage
800 MWIn study Jefferson, ORWest Jun 2023target 2025
Solar + storage project 23-234, Jefferson County
Solar + storage
800 MWIn study Jefferson, ORWest Jun 2023target 2025
Wind + storage project G1041, Sherman County
Wind + storage
750 MWIn study Sherman, ORWest Nov 2023target 2027
Other project 23-229, Jefferson County
Other
750 MWIn study Jefferson, ORWest Mar 2023target 2027
Gas project G0752, Morrow County
Gas
670 MWIn study Morrow, ORWest Jun 2022target 2025
Battery storage project G1056, Deschutes County
Battery storage
650 MWIn study Deschutes, ORWest Nov 2023target 2030
Battery storage project G0963, Morrow County
Battery storage
650 MWIn study Morrow, ORWest Oct 2023target 2030
Battery storage project G0948, Sherman County
Battery storage
650 MWIn study Sherman, ORWest Oct 2023target 2028
Battery storage project G0947, Sherman County
Battery storage
650 MWIn study Sherman, ORWest Oct 2023target 2028
Battery storage project G0796, Sherman County
Battery storage
650 MWIn study Sherman, ORWest Aug 2022target 2029
Battery storage project G0778, Umatilla County
Battery storage
650 MWIn study Umatilla, ORWest Aug 2022target 2027
Battery storage project G0965, Umatilla County
Battery storage
650 MWIn study Umatilla, ORWest Oct 2023target 2032
Battery storage project G0774, Wasco County
Battery storage
650 MWIn study Wasco, ORWest Aug 2022target 2028
Battery storage project G0946, Sherman County
Battery storage
650 MWIn study Sherman, ORWest Oct 2023target 2028
Battery storage project G0792, Sherman County
Battery storage
650 MWIn study Sherman, ORWest Aug 2022target 2029
Solar + storage project T2-070, Harney County
Solar + storage
640 MWIn study Harney, ORWest Sep 2025target 2028
Battery storage project G0807, Douglas County
Battery storage
600 MWIn study Douglas, ORWest Sep 2022target 2030
Battery storage project G0642, Crook County
Battery storage
600 MWIn study Crook, ORWest Feb 2020target 2025
Solar project G0669, Crook County
Solar
600 MWIn study Crook, ORWest Feb 2021target 2027
Battery storage project G0812, Lane County
Battery storage
600 MWIn study Lane, ORWest Sep 2022target 2030
Page 1 of 7

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)