United States › Grid › Interconnection queues › Oregon
GAS · WESTGas project G0752, Morrow County
Gas project G0752, Morrow County is a 670 MW gas request in interconnection study in the West interconnection queue, in Morrow County, Oregon.
Queue statusIn planning
- PlanningQueued Jun 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- G0752
- Grid region
- West (non-ISO utilities)
- Connection point (POI)
- 5-mile 500kV Gen Tie to Longhorn 500 kV Substation
- Location
- Morrow County, Oregon
- Technology
- Gas: 340 MW · Battery: 330 MW
- Total requested
- 670 MW
- Service type
- Energy only (ERIS)
- Study phase
- In Progress (unknown study)
- Queue status
- Active
- Entered queue
- 16 June 2022
- Proposed online date
- December 2025
Location
Marker shows the centre of Morrow County; the queue data does not give exact sites.
Other requests in Morrow County
- Solar project G0678, Morrow CountySolar · 1,200 MW · in study
- Battery storage project G0963, Morrow CountyBattery storage · 650 MW · in study
- Solar + storage project T2-008, Morrow CountySolar + storage · 500 MW · in study
- Solar + storage project G0478, Morrow CountySolar + storage · 500 MW · in study
- Solar + storage project T2-031, Morrow CountySolar + storage · 400 MW · in study
- Solar + storage project T2-087, Morrow CountySolar + storage · 400 MW · in study
- Solar + storage project T2-030, Morrow CountySolar + storage · 400 MW · in study
- Solar + storage project T2-086, Morrow CountySolar + storage · 400 MW · in study
- Onshore wind project G0366, Morrow CountyOnshore wind · 302 MW · in study
- Solar project G0944, Morrow CountySolar · 261 MW · in study
- Onshore wind project G0435, Morrow CountyOnshore wind · 238 MW · in study
- Solar + storage project T2-021, Morrow CountySolar + storage · 200 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem