Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown25124.3 GW
Active in queue24.3 GW251 requests
Agreement signed860 MW7 requests
Withdrawn47276.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

251 requests · page 1 of 6
ProjectCapacityStatusLocationRegionQueuedOnline
Nuclear project 107, Miami-Dade County
Nuclear · FPL
1,300 MWIn study Miami-Dade, FLSoutheast Aug 2007target 2027
Nuclear project 108, Miami-Dade County
Nuclear · FPL
1,300 MWIn study Miami-Dade, FLSoutheast Aug 2007target 2028
Gas project JEA-Q008, Duval County
Gas
645 MWIn study Duval, FLSoutheast Feb 2018target 2030
Gas project 137, Pasco County
Gas · Seminole Electric Cooperative, Inc.
575 MWUnder construction Pasco, FLSoutheast Nov 2015target 2020
Bull Creek (Osceola Generating Station)
Gas
555 MWAgreement signed Osceola, FLSoutheast Sep 2021target 2025
Gas project 4, Osceola County
Gas · Orlando Utilities Commission
537 MWIn study Osceola, FLSoutheast Apr 1999
Battery storage project 620, Bay County
Battery storage · FPL
400 MWIn study Bay, FLSoutheast Jan 2024target 2026
Gas project FC100382, Osceola County
Gas · Duke Energy Florida, LLC
265 MWIn study Osceola, FLSoutheast Dec 2025target 2030
Gas project FC100386, Osceola County
Gas · Duke Energy Florida, LLC
265 MWIn study Osceola, FLSoutheast Dec 2025target 2030
Malta Project
Battery storage
225 MWIn study Brevard, FLSoutheast Mar 2023target 2026
Battery storage project 292, Pinellas County
Battery storage · Duke Energy Florida, LLC
225 MWUnder construction Pinellas, FLSoutheast Apr 2021target 2025
Battery storage project 615, Putnam County
Battery storage · FPL
200 MWIn study Putnam, FLSoutheast Jan 2024target 2027
Battery storage project FC100380, Citrus County
Battery storage · Duke Energy Florida, LLC
199 MWIn study Citrus, FLSoutheast Dec 2025target 2030
Battery storage project FC100009, Pasco County
Battery storage · Duke Energy Florida, LLC
199 MWIn study Pasco, FLSoutheast Dec 2024target 2029
Gas project 328, Pinellas County
Gas · Duke Energy Florida, LLC
172 MWUnder construction Pinellas, FLSoutheast Jun 2023target 2024
Gas project 22
Gas
136 MWIn study FLSoutheast Aug 2018target 2019
Gas project 118, Polk County
Gas
132 MWIn study Polk, FLSoutheast Apr 2025target 2026
Battery storage project 327, Citrus County
Battery storage · Duke Energy Florida, LLC
100 MWUnder construction Citrus, FLSoutheast May 2023target 2027
Battery storage project FC100008, Highlands County
Battery storage · Duke Energy Florida, LLC
100 MWIn study Highlands, FLSoutheast Dec 2024target 2029
Battery storage project FC100381, Leon County
Battery storage · Duke Energy Florida, LLC
100 MWIn study Leon, FLSoutheast Dec 2025target 2031
Gas project 415, Manatee County
Gas · FPL
87.0 MWIn study Manatee, FLSoutheast Sep 2020target 2026
Gas project 333, Polk County
Gas · Duke Energy Florida, LLC
84.0 MWUnder construction Polk, FLSoutheast Jul 2023target 2025
Gas project 417, Volusia County
Gas · FPL
76.0 MWIn study Volusia, FLSoutheast Sep 2020target 2025
Solar + storage project 425A, Jackson County
Solar + storage · Third Party
75.0 MWAgreement signed Jackson, FLSoutheast Feb 2022target 2029
Solar project 344, Madison County
Solar · Duke Energy Florida, LLC
74.9 MWUnder construction Madison, FLSoutheast Jan 2024target 2026
Solar project 259, Highlands County
Solar · Placid Solar II, LLC
74.9 MWUnder construction Highlands, FLSoutheast May 2019target 2023
Solar project 218, Suwannee County
Solar · Twin Rivers Solar, LLC
74.9 MWIn study Suwannee, FLSoutheast Feb 2018target 2020
Solar project 605, Desoto County
Solar · FPL
74.9 MWIn study Desoto, FLSoutheast Dec 2023target 2032
Solar project FC100384, Suwannee County
Solar · Duke Energy Florida, LLC
74.9 MWIn study Suwannee, FLSoutheast Dec 2025target 2030
Solar project 343, Orange County
Solar · Duke Energy Florida, LLC
74.9 MWUnder construction Orange, FLSoutheast Jan 2024target 2028
Solar project FC100007, Madison County
Solar · Duke Energy Florida, LLC
74.9 MWIn study Madison, FLSoutheast Nov 2024target 2028
Solar project 326, Osceola County
Solar · Duke Energy Florida, LLC
74.9 MWUnder construction Osceola, FLSoutheast May 2023target 2027
Solar project 604, Desoto County
Solar · FPL
74.9 MWIn study Desoto, FLSoutheast Dec 2023target 2032
Solar project FC100018, Liberty County
Solar · Duke Energy Florida, LLC
74.9 MWIn study Liberty, FLSoutheast Dec 2024target 2028
Solar project 307, Suwannee County
Solar · CP Ironwood, LLC
74.9 MWPaused / redesign Suwannee, FLSoutheast Apr 2022target 2026
Solar project 342, Orange County
Solar · Duke Energy Florida, LLC
74.9 MWUnder construction Orange, FLSoutheast Jan 2024target 2027
Solar project 258, Highlands County
Solar · Placid Solar, LLC
74.9 MWUnder construction Highlands, FLSoutheast May 2019target 2023
Solar + storage project JEA-Q012, Duval County
Solar + storage
74.9 MWIn study Duval, FLSoutheast May 2024target 2027
Solar + storage project JEA-Q010, Duval County
Solar + storage
74.9 MWIn study Duval, FLSoutheast May 2024target 2026
Solar project FC100012, Hamilton County
Solar · Duke Energy Florida, LLC
74.9 MWIn study Hamilton, FLSoutheast Nov 2024target 2028
Solar project 323, Jackson County
Solar · Duke Energy Florida, LLC
74.9 MWUnder construction Jackson, FLSoutheast Feb 2023target 2027
Solar project 202.1, Levy County
Solar · FL SB 9, LLC
74.9 MWUnder construction Levy, FLSoutheast Oct 2017target 2021
Solar project 610, Charlotte County
Solar · FPL
74.9 MWIn study Charlotte, FLSoutheast Dec 2023target 2032
Solar project 319, Hernando County
Solar · Duke Energy Florida, LLC
74.9 MWPaused / redesign Hernando, FLSoutheast Dec 2022target 2026
Solar project FC100004, Sumter County
Solar · Duke Energy Florida, LLC
74.9 MWIn study Sumter, FLSoutheast Nov 2024target 2028
Solar project 273, Polk County
Solar · FL Solar 10, LLC
74.9 MWUnder construction Polk, FLSoutheast Dec 2019target 2022
Solar + storage project JEA-Q009, Duval County
Solar + storage
74.9 MWIn study Duval, FLSoutheast Jul 2021target 2026
Solar project 607, Charlotte County
Solar · FPL
74.9 MWIn study Charlotte, FLSoutheast Dec 2023target 2032
Solar project 608, Charlotte County
Solar · FPL
74.9 MWIn study Charlotte, FLSoutheast Dec 2023target 2032
Solar project 612, Charlotte County
Solar · FPL
74.9 MWIn study Charlotte, FLSoutheast Dec 2023target 2032
Page 1 of 6

Capacity in the queue by state

Click a state to drill down.

By grid region

ISO/RTO markets and the non-ISO West and Southeast.

Requests by year joined

Capacity of requests in this view, by the year they entered the queue. Click a year.

20152025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)