United States › Grid › Interconnection queues › Florida

SOLAR · SOUTHEAST

Solar project 273, Polk County

Solar project 273, Polk County is a 74.9 MW solar request under construction in the Southeast interconnection queue, in Polk County, Florida, connecting to Duke Energy Florida.

Queue statusUnder construction
  1. PlanningQueued Dec 2019 (completed)
  2. Consented (completed)
  3. Construction (current stage)
  4. OperatingTarget Dec 2022 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
273
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Duke Energy Florida
Developer
FL Solar 10, LLC
Connection point (POI)
Tiger Bay Substation
Location
Polk County, Florida
Technology
Solar: 74.9 MW
Total requested
74.9 MW
Service type
NRIS and ERIS
Study phase
Construction
Queue status
Active
Entered queue
17 December 2019
Proposed online date
December 2022

Location

Marker shows the centre of Polk County; the queue data does not give exact sites.

Power plants in Florida · Transmission lines in Florida

Other requests in Polk County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem