United States βΊ Grid βΊ Interconnection queues
GAS Β· SOUTHEASTGas project 1
Gas project 1 is a 567 MW gas request built and operating in the Southeast interconnection queue, connecting to Duke Energy Florida.
Request details
- Queue ID
- 1
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Duke Energy Florida
- Developer
- Duke Energy Florida, LLC
- Connection point (POI)
- Hines Substation 230 kV
- Technology
- Gas: 567 MW
- Total requested
- 567 MW
- Service type
- Network resource (NRIS)
- Study phase
- IA Executed
- Queue status
- Operational
- Entered queue
- 1 April 1997
Location
Marker shows the centre of County; the queue data does not give exact sites.
Other requests in County
- Gas project 333, Polk CountyGas Β· 84.0 MW Β· under construction
- Solar project 273, Polk CountySolar Β· 74.9 MW Β· under construction
- Solar project 76, Polk CountySolar Β· 55.0 MW Β· agreement signed
- Other project 70, Polk CountyOther Β· 48.0 MW Β· agreement signed
- Gas project 118, Polk CountyGas Β· 132 MW Β· in study
- Solar project 111, Polk CountySolar Β· 52.0 MW Β· in study
- Battery storage project 120, Polk CountyBattery storage Β· 20.0 MW Β· in study
- Solar project 123, Polk CountySolar Β· 19.5 MW Β· in study
- Gas project 2, Polk CountyGas Β· 1,701 MW Β· built
- Gas project 2Gas Β· 701 MW Β· built
- Gas project 135, Polk CountyGas Β· 637 MW Β· built
- Gas project 1, Polk CountyGas Β· 567 MW Β· built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem