πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

GAS Β· SOUTHEAST

Gas project 1

Gas project 1 is a 567 MW gas request built and operating in the Southeast interconnection queue, connecting to Duke Energy Florida.

Queue statusOperating
  1. PlanningQueued Apr 1997 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. Operating (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
1
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Duke Energy Florida
Developer
Duke Energy Florida, LLC
Connection point (POI)
Hines Substation 230 kV
Technology
Gas: 567 MW
Total requested
567 MW
Service type
Network resource (NRIS)
Study phase
IA Executed
Queue status
Operational
Entered queue
1 April 1997

Location

Marker shows the centre of County; the queue data does not give exact sites.

Power plants in Β· Transmission lines in

Other requests in County