🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Florida

OTHER · SOUTHEAST

Other project 70, Polk County

Other project 70, Polk County is a 48.0 MW other request with a signed interconnection agreement in the Southeast interconnection queue, in Polk County, Florida, connecting to Tampa Electric Company.

Queue statusConsented
  1. PlanningQueued May 2020 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2021 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
70
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Tampa Electric Company
Connection point (POI)
Mulberry Substation, Polk County, Florida
Location
Polk County, Florida
Technology
Other: 48.0 MW
Total requested
48.0 MW
Service type
Energy only (ERIS)
Study phase
Interconnection Agreement Executed
Queue status
Active
Entered queue
21 May 2020
Proposed online date
July 2021

Location

Marker shows the centre of Polk County; the queue data does not give exact sites.

Power plants in Florida · Transmission lines in Florida

Other requests in Polk County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem