Solar project 76, Polk County

Solar project 76, Polk County is a 55.0 MW solar request with a signed interconnection agreement in the Southeast interconnection queue, in Polk County, Florida, connecting to Tampa Electric Company.

Queue statusConsented
  1. PlanningQueued Nov 2020 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2023 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
76
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Tampa Electric Company
Connection point (POI)
Pebbledale Substation, Polk County, Florida
Location
Polk County, Florida
Technology
Solar: 55.0 MW
Total requested
55.0 MW
Service type
Network resource (NRIS)
Study phase
Interconnection Agreement Executed
Queue status
Active
Entered queue
30 November 2020
Proposed online date
November 2023

Location

Marker shows the centre of Polk County; the queue data does not give exact sites.