Interconnection queue in Delaware

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown16874 MW
Active in queue874 MW16 requests
Agreement signed50.0 MW3 requests
Withdrawn10317.6 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

16 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Maryland Offshore Wind Energy Project (MOWEP)
Offshore wind
248 MWPaused / redesign Sussex, DEPJM Aug 2015target 2027
Battery storage project AH2-051, New Castle County
Battery storage
200 MWIn study New Castle, DEPJM Dec 2021target 2025
Battery storage project AH2-077, Sussex County
Battery storage
150 MWIn study Sussex, DEPJM Jan 2022target 2027
Solar project AH1-672, Sussex County
Solar Β· TerraForm Freeman Solar, LLC
75.0 MWIn study Sussex, DEPJM Dec 2024
Cedar Creek Solar
Solar
20.0 MWPaused / redesign Kent, DEPJM Apr 2017target 2027
Cedar Creek Solar
Solar
20.0 MWPaused / redesign Kent, DEPJM Apr 2017target 2027
Raceway Solar
Solar
20.0 MWAgreement signed Kent, DEPJM Mar 2017target 2025
Solar project AG2-447, New Castle County
Solar Β· Freepoint Solar LLC
20.0 MWIn study New Castle, DEPJM Feb 2025target 2024
Raceway Solar
Solar
20.0 MWAgreement signed Kent, DEPJM Mar 2017target 2025
Cedar Creek Solar
Solar
19.8 MWPaused / redesign New Castle, DEPJM Oct 2016target 2027
Cedar Creek Solar
Solar
19.8 MWPaused / redesign New Castle, DEPJM Oct 2016target 2027
Cedar Creek Solar
Solar
18.8 MWPaused / redesign New Castle, DEPJM Oct 2016target 2027
Cedar Creek Solar
Solar
15.9 MWPaused / redesign New Castle, DEPJM Oct 2016target 2027
Raceway Solar
Solar
10.0 MWAgreement signed Kent, DEPJM Apr 2017target 2025
Other project AI2-025, New Castle County
Other
10.0 MWIn study New Castle, DEPJM Dec 2022target 2026
Maryland Offshore Wind Energy Project (MOWEP)
Offshore wind
7.3 MWPaused / redesign Sussex, DEPJM Apr 2019target 2027

Capacity in the queue by state

Click a state to drill down.

By grid region

ISO/RTO markets and the non-ISO West and Southeast.

Requests by year joined

Capacity of requests in this view, by the year they entered the queue. Click a year.

20152025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)