๐Ÿ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more โ†’ Skip to main content

United States โ€บ Grid โ€บ Interconnection queues โ€บ West Virginia

OCTARY USA ยท INTERCONNECTION QUEUES

Interconnection queue in West Virginia

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown416,900 MW
Active in queue6,900 MW41 requests
Agreement signed1,291 MW11 requests
Withdrawn16121.0 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

41 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project AG2-582, Doddridge County
Gas ยท CPV Shay, LLC
2,100 MWIn study Doddridge, WVPJM Feb 2025target 2026
Maidsville CCGT
Gas
1,270 MWPaused / redesign Preston, WVPJM Sep 2018target 2026
Glen Falls Facility
Gas
550 MWAgreement signed Harrison, WVPJM Apr 2015target 2029
Solar + storage project AH2-043, Kanawha County
Solar + storage
200 MWIn study Kanawha, WVPJM Nov 2021target 2025
Onshore wind project AH2-386, Pendleton County
Onshore wind
192 MWIn study Pendleton, WVPJM Mar 2022target 2027
Mount Storm Repower
Onshore wind ยท Renew Development Holdco LLC
171 MWIn study Barbour, WVPJM Jan 2025target 2025
Deep Lake Solar
Solar
150 MWAgreement signed Nicholas, WVPJM Mar 2020target 2029
CPV Capon Springs Wind
Onshore wind ยท CPV Springs Wind, LLC
150 MWIn study Hampshire, WVPJM Jan 2025target 2025
Solar + storage project AI2-445, Tucker County
Solar + storage
148 MWIn study Tucker, WVPJM Mar 2023target 2026
Onshore wind project AG2-062, Grant County
Onshore wind ยท Catamount Wind LLC
147 MWIn study Grant, WVPJM Feb 2025target 2022
Solar project AH1-188, Mingo County
Solar ยท Twisted Gun Solar, LLC
140 MWIn study Mingo, WVPJM Feb 2025target 2025
Onshore wind project AI1-006, Randolph County
Onshore wind
103 MWIn study Randolph, WVPJM Apr 2022target 2026
Nicholas Solar
Solar
100 MWAgreement signed Nicholas, WVPJM Mar 2020target 2029
New Haven Solar
Solar
100 MWAgreement signed Mason, WVPJM Mar 2020target 2028
Brandonville Solar
Solar
99.6 MWPaused / redesign Preston, WVPJM Sep 2018target 2026
Rippon
Solar
99.0 MWAgreement signed Jefferson, WVPJM Mar 2019target 2026
Solar project AH2-030, Jefferson County
Solar
90.0 MWIn study Jefferson, WVPJM Nov 2021target 2025
Solar project AG2-657, Fayette County
Solar ยท Mammoth Solar, LLC
90.0 MWIn study Fayette, WVPJM Feb 2025target 2024
Raleigh Solar Project
Solar
90.0 MWPaused / redesign Raleigh, WVPJM Sep 2018target 2025
Solar project AG2-423, Barbour County
Solar ยท Falling Waters Solar, LLC
80.0 MWIn study Barbour, WVPJM Jan 2025target 2024
Solar project AG2-568
Solar ยท Sundial Energy, LLC
80.0 MWIn study WVPJM Feb 2025target 2024
Franklintown Farm Solar and BESS
Solar + storage
80.0 MWAgreement signed Jefferson, WVPJM Sep 2020target 2028
Short Mountain Wind Energy
Onshore wind
80.0 MWPaused / redesign Hardy, WVPJM Sep 2017target 2024
Solar + storage project AI1-211, Preston County
Solar + storage
68.0 MWIn study Preston, WVPJM Sep 2022target 2024
Solar + storage project AI2-444
Solar + storage
59.5 MWIn study WVPJM Mar 2023target 2026
Hawks Nest Hydro
Hydro
51.0 MWAgreement signed Fayette, WVPJM Mar 2019target 2028
Mea Nug
Other
50.0 MWAgreement signed Monongalia, WVPJM Sep 2020target 2028
Solar project AG2-448, Mineral County
Solar ยท Potomac Hills Energy, LLC
50.0 MWIn study Mineral, WVPJM Feb 2025target 2024
Glen Falls Facility
Gas
45.0 MWAgreement signed Harrison, WVPJM Mar 2018target 2029
Gas project AI1-192, Marion County
Gas
40.0 MWIn study Marion, WVPJM Sep 2022target 2024
Solar project AI2-332, Nicholas County
Solar
40.0 MWIn study Nicholas, WVPJM Mar 2023target 2030
Mountaineer #1
Coal
36.0 MWAgreement signed WVPJM Oct 20152018
Battery storage project AH2-031, Jefferson County
Battery storage
30.0 MWIn study Jefferson, WVPJM Nov 2021target 2025
Glen Falls Facility
Gas
30.0 MWAgreement signed Harrison, WVPJM Sep 2016target 2029
Solar project AI2-339, Nicholas County
Solar
26.8 MWIn study Nicholas, WVPJM Mar 2023target 2024
Solar project AH2-041, Monongalia County
Solar
18.9 MWIn study Monongalia, WVPJM Nov 2021target 2023
Solar project AI2-182, Preston County
Solar
12.0 MWIn study Preston, WVPJM Feb 2023target 2025
Solar project AH2-040, Tucker County
Solar
11.5 MWIn study Tucker, WVPJM Nov 2021target 2024
Solar project AH2-038, Hancock County
Solar
10.8 MWIn study Hancock, WVPJM Nov 2021target 2024
Solar project AH2-042, Berkeley County
Solar
5.8 MWIn study Berkeley, WVPJM Nov 2021target 2024
Solar project AH2-039, Marion County
Solar
5.5 MWIn study Marion, WVPJM Nov 2021target 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)