Brandonville Solar

Brandonville Solar is a 99.6 MW solar request suspended in the PJM interconnection queue, in Preston County, West Virginia, connecting to APS.

Queue statusPaused / redesign
  1. PlanningQueued Sep 2018 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AE1-106
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
APS
Connection point (POI)
Lake Lynn-Hazelton 138 kV
Location
Preston County, West Virginia
Technology
Solar: 99.6 MW
Total requested
99.6 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Suspended
Entered queue
11 September 2018
Proposed online date
December 2026

Location

Marker shows the centre of Preston County; the queue data does not give exact sites.