🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › West Virginia

ONSHORE WIND · PJM

North Briery WF

North Briery WF is a 60.0 MW onshore wind request withdrawn in the PJM interconnection queue, in Preston County, West Virginia, connecting to APS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2005 (completed)
  2. Withdrawn / abandonedFeb 2012 (project stopped here)
  3. ConsentedSep 2008 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
N33
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
APS
Connection point (POI)
Afton 138kV
Location
Preston County, West Virginia
Technology
Wind: 60.0 MW
Total requested
60.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Withdrawn
Entered queue
28 January 2005
Agreement signed
23 September 2008
Proposed online date
December 2012
Withdrawn
February 2012

Location

Marker shows the centre of Preston County; the queue data does not give exact sites.

Power plants in West Virginia · Transmission lines in West Virginia

Other requests in Preston County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem