🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › West Virginia

SOLAR · PJM

Glade Run Solar Energy Center

Glade Run Solar Energy Center is a 50.0 MW solar request withdrawn in the PJM interconnection queue, in Preston County, West Virginia, connecting to APS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2020 (completed)
  2. Withdrawn / abandonedJan 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG1-233
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
APS
Connection point (POI)
Hazleton - Lake Lynn 138 kV
Location
Preston County, West Virginia
Technology
Solar: 50.0 MW
Total requested
50.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Withdrawn
Entered queue
25 September 2020
Proposed online date
June 2028
Withdrawn
January 2025

Location

Marker shows the centre of Preston County; the queue data does not give exact sites.

Power plants in West Virginia · Transmission lines in West Virginia

Other requests in Preston County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem