United States › Grid › Interconnection queues › West Virginia
SOLAR · PJMSolar project AI2-182, Preston County
Solar project AI2-182, Preston County is a 12.0 MW solar request in interconnection study in the PJM interconnection queue, in Preston County, West Virginia, connecting to APS.
- PlanningQueued Feb 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AI2-182
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- APS
- Connection point (POI)
- Jennings-Hazelton 138kV II
- Location
- Preston County, West Virginia
- Technology
- Solar: 12.0 MW
- Total requested
- 12.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Active
- Entered queue
- 28 February 2023
- Proposed online date
- December 2025
Location
Marker shows the centre of Preston County; the queue data does not give exact sites.
Power plants in West Virginia · Transmission lines in West Virginia
Other requests in Preston County
- Solar + storage project AI1-211, Preston CountySolar + storage · 68.0 MW · in study
- Maidsville CCGTGas · 1,270 MW · suspended
- Brandonville SolarSolar · 99.6 MW · suspended
- Gas project D08_W18, Preston CountyGas · 88.0 MW · withdrawn
- Onshore wind project P52, Preston CountyOnshore wind · 80.0 MW · withdrawn
- Onshore wind project AD1-068, Preston CountyOnshore wind · 80.0 MW · withdrawn
- Solar + storage project AH2-255, Preston CountySolar + storage · 70.0 MW · withdrawn
- Solar project AH2-260, Preston CountySolar · 70.0 MW · withdrawn
- Solar project AH1-593, Preston CountySolar · 65.0 MW · withdrawn
- Onshore wind project Q55, Preston CountyOnshore wind · 62.5 MW · withdrawn
- North Briery WFOnshore wind · 60.0 MW · withdrawn
- Glade Run Solar Energy CenterSolar · 50.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem