SOLAR + STORAGE Β· PJMSolar + storage project AH2-255, Preston County
Solar + storage project AH2-255, Preston County is a 70.0 MW solar + storage request withdrawn in the PJM interconnection queue, in Preston County, West Virginia, connecting to APS.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2022 (completed)
- Withdrawn / abandonedApr 2022 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AH2-255
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- APS
- Location
- Preston County, West Virginia
- Technology
- Solar: 70.0 MW Β· Battery
- Total requested
- 70.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 9 March 2022
- Proposed online date
- November 2025
- Withdrawn
- April 2022
Location
Marker shows the centre of Preston County; the queue data does not give exact sites.
Power plants in West Virginia Β· Transmission lines in West Virginia
Other requests in Preston County
- Solar + storage project AI1-211, Preston CountySolar + storage Β· 68.0 MW Β· in study
- Solar project AI2-182, Preston CountySolar Β· 12.0 MW Β· in study
- Maidsville CCGTGas Β· 1,270 MW Β· suspended
- Brandonville SolarSolar Β· 99.6 MW Β· suspended
- Gas project D08_W18, Preston CountyGas Β· 88.0 MW Β· withdrawn
- Onshore wind project P52, Preston CountyOnshore wind Β· 80.0 MW Β· withdrawn
- Onshore wind project AD1-068, Preston CountyOnshore wind Β· 80.0 MW Β· withdrawn
- Solar project AH2-260, Preston CountySolar Β· 70.0 MW Β· withdrawn
- Solar project AH1-593, Preston CountySolar Β· 65.0 MW Β· withdrawn
- Onshore wind project Q55, Preston CountyOnshore wind Β· 62.5 MW Β· withdrawn
- North Briery WFOnshore wind Β· 60.0 MW Β· withdrawn
- Glade Run Solar Energy CenterSolar Β· 50.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem