SOLAR Β· PJM

Solar project AG2-568

Solar project AG2-568 is a 80.0 MW solar request in interconnection study in the PJM interconnection queue, connecting to AEP.

Queue statusIn planning
  1. PlanningQueued Feb 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Feb 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AG2-568
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Developer
Sundial Energy, LLC
Connection point (POI)
Stink Run - Sundial 138 kV
Location
West Virginia
Technology
Solar: 80.0 MW
Total requested
80.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Active
Entered queue
21 February 2025
Proposed online date
February 2024

Location

No county location in the queue data.