ONSHORE WIND · PJMCPV Capon Springs Wind
CPV Capon Springs Wind is a 150 MW onshore wind request in interconnection study in the PJM interconnection queue, in Hampshire County, West Virginia, connecting to APS.
- PlanningQueued Jan 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jan 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AH1-387
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- APS
- Developer
- CPV Springs Wind, LLC
- Connection point (POI)
- Meadowbrook-Greenland Gap 500kV
- Location
- Hampshire County, West Virginia
- Technology
- Wind: 150 MW
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Study phase
- System Impact Study
- Queue status
- Active
- Entered queue
- 30 January 2025
- Proposed online date
- January 2025
Location
Marker shows the centre of Hampshire County; the queue data does not give exact sites.
Power plants in West Virginia · Transmission lines in West Virginia
Other requests in Hampshire County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem