United States βΊ Grid βΊ Interconnection queues βΊ West Virginia
SOLAR Β· PJMSolar project AD2-157, Hampshire County
Solar project AD2-157, Hampshire County is a 100 MW solar request withdrawn in the PJM interconnection queue, in Hampshire County, West Virginia, connecting to APS.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2018 (completed)
- Withdrawn / abandonedOct 2022 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AD2-157
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- APS
- Connection point (POI)
- Hampshire-Gore 138kV
- Location
- Hampshire County, West Virginia
- Technology
- Solar: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Withdrawn
- Entered queue
- 23 March 2018
- Proposed online date
- December 2021
- Withdrawn
- October 2022
Location
Marker shows the centre of Hampshire County; the queue data does not give exact sites.