Capon Bridge Solar

Capon Bridge Solar is a 20.0 MW solar request built and operating in the PJM interconnection queue, in Hampshire County, West Virginia, connecting to APS.

Queue statusOperating
  1. PlanningQueued Sep 2018 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingJul 2024 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
AE1-109
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
APS
Connection point (POI)
Frenchs Mill 34 kV
Location
Hampshire County, West Virginia
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
Queue status
Operational
Entered queue
15 September 2018
Proposed online date
July 2024
Came online
July 2024

Location

Marker shows the centre of Hampshire County; the queue data does not give exact sites.

Power plants in West Virginia · Transmission lines in West Virginia

Other requests in Hampshire County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem