United States β€Ί Grid β€Ί Interconnection queues β€Ί Rhode Island

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Rhode Island

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown3982 MW
Active in queue982 MW3 requests
Agreement signed982 MW3 requests
Withdrawn9110.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

3 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Revoultion Offshore wind
Offshore wind
704 MWAgreement signed RIISO-NE Sep 2018target 2026
Battery Storage
Battery storage
205 MWAgreement signed Washington, RIISO-NE Sep 2021target 2029
Ocean State Power uprate
Gas
73.2 MWAgreement signed Providence, RIISO-NE Apr 2018target 2026

Capacity in the queue by state

Click a state to drill down.

By grid region

ISO/RTO markets and the non-ISO West and Southeast.

Requests by year joined

Capacity of requests in this view, by the year they entered the queue. Click a year.

20182021

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)