United States › Grid › Interconnection queues › Rhode Island
BATTERY STORAGE · ISO-NEBattery Storage
Battery Storage is a 205 MW battery storage request with a signed interconnection agreement in the ISO-NE interconnection queue, in Washington County, Rhode Island.
Queue statusConsented
- PlanningQueued Sep 2021 (completed)
- ConsentedNov 2025 (current stage)
- Construction (not yet reached)
- OperatingTarget Dec 2029 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 1163
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- RIE L190-2 (0.615 miles from Davisville and 1.935 miles from Old Baptist substations).
- Location
- Washington County, Rhode Island
- Technology
- Battery: 205 MW
- Total requested
- 205 MW
- Service type
- Energy only (ERIS)
- Study phase
- Executed
- Queue status
- Active
- Entered queue
- 22 September 2021
- Agreement signed
- 24 November 2025
- Proposed online date
- December 2029
Location
Marker shows the centre of Washington County; the queue data does not give exact sites.
Power plants in Rhode Island · Transmission lines in Rhode Island
Other requests in Washington County
- Block Island Wind FarmOnshore wind · 29.0 MW · built
- Alton SolarSolar · 13.9 MW · built
- Chase Hill Substation - NG Western RI DG Area StudySolar · 6.8 MW · built
- WindOnshore wind · 536 MW · withdrawn
- WindOnshore wind · 385 MW · withdrawn
- Battery StorageBattery storage · 313 MW · withdrawn
- Battery StorageBattery storage · 180 MW · withdrawn
- Solar (QF)Solar · 56.5 MW · withdrawn
- Wood River Substation - Western RI DER Study #3Solar · 49.0 MW · withdrawn
- Solar (QF)Solar · 40.0 MW · withdrawn
- Wood River - NG WRI DG Area Study #2 >5 MWSolar · 34.4 MW · withdrawn
- SolarSolar · 30.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem