United States › Grid › Interconnection queues › Rhode Island

BATTERY STORAGE · ISO-NE

Battery Storage

Battery Storage is a 313 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Washington County, Rhode Island.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2024 (completed)
  2. Withdrawn / abandonedOct 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1568
Grid region
ISO-NE (New England)
Connection point (POI)
The Primary Point of Interconnection will be a direct interconnection to the 115-kV bus at Davisville Substation Expansion owned by RI_NGRID.
Location
Washington County, Rhode Island
Technology
Battery: 313 MW
Total requested
313 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
12 June 2024
Proposed online date
January 2027
Withdrawn
October 2025

Location

Marker shows the centre of Washington County; the queue data does not give exact sites.

Power plants in Rhode Island · Transmission lines in Rhode Island

Other requests in Washington County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem