United States › Grid › Interconnection queues › Rhode Island
BATTERY STORAGE · ISO-NEBattery Storage
Battery Storage is a 313 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Washington County, Rhode Island.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2024 (completed)
- Withdrawn / abandonedOct 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1568
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- The Primary Point of Interconnection will be a direct interconnection to the 115-kV bus at Davisville Substation Expansion owned by RI_NGRID.
- Location
- Washington County, Rhode Island
- Technology
- Battery: 313 MW
- Total requested
- 313 MW
- Service type
- Network resource (NRIS)
- Queue status
- Withdrawn
- Entered queue
- 12 June 2024
- Proposed online date
- January 2027
- Withdrawn
- October 2025
Location
Marker shows the centre of Washington County; the queue data does not give exact sites.
Power plants in Rhode Island · Transmission lines in Rhode Island
Other requests in Washington County
- Battery StorageBattery storage · 205 MW · agreement signed
- Block Island Wind FarmOnshore wind · 29.0 MW · built
- Alton SolarSolar · 13.9 MW · built
- Chase Hill Substation - NG Western RI DG Area StudySolar · 6.8 MW · built
- WindOnshore wind · 536 MW · withdrawn
- WindOnshore wind · 385 MW · withdrawn
- Battery StorageBattery storage · 180 MW · withdrawn
- Solar (QF)Solar · 56.5 MW · withdrawn
- Wood River Substation - Western RI DER Study #3Solar · 49.0 MW · withdrawn
- Solar (QF)Solar · 40.0 MW · withdrawn
- Wood River - NG WRI DG Area Study #2 >5 MWSolar · 34.4 MW · withdrawn
- SolarSolar · 30.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem