United States › Grid › Interconnection queues › Rhode Island
SOLAR · ISO-NEWood River - NG WRI DG Area Study #2 >5 MW
Wood River - NG WRI DG Area Study #2 >5 MW is a 34.4 MW solar request withdrawn in the ISO-NE interconnection queue, in Washington County, Rhode Island, connecting to NGRID.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2020 (completed)
- Withdrawn / abandonedOct 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1042
- Grid region
- ISO-NE (New England)
- Utility / transmission owner
- NGRID
- Connection point (POI)
- NG Wood River Substation, feeder 85T2
- Location
- Washington County, Rhode Island
- Technology
- Solar: 34.4 MW
- Total requested
- 34.4 MW
- Queue status
- Withdrawn
- Entered queue
- 19 August 2020
- Proposed online date
- June 2025
- Withdrawn
- October 2024
Location
Marker shows the centre of Washington County; the queue data does not give exact sites.
Power plants in Rhode Island · Transmission lines in Rhode Island
Other requests in Washington County
- Battery StorageBattery storage · 205 MW · agreement signed
- Block Island Wind FarmOnshore wind · 29.0 MW · built
- Alton SolarSolar · 13.9 MW · built
- Chase Hill Substation - NG Western RI DG Area StudySolar · 6.8 MW · built
- WindOnshore wind · 536 MW · withdrawn
- WindOnshore wind · 385 MW · withdrawn
- Battery StorageBattery storage · 313 MW · withdrawn
- Battery StorageBattery storage · 180 MW · withdrawn
- Solar (QF)Solar · 56.5 MW · withdrawn
- Wood River Substation - Western RI DER Study #3Solar · 49.0 MW · withdrawn
- Solar (QF)Solar · 40.0 MW · withdrawn
- SolarSolar · 30.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem