United States โ€บ Grid โ€บ Interconnection queues โ€บ Illinois

OCTARY USA ยท INTERCONNECTION QUEUES

Interconnection queue in Illinois

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown42374.6 GW
Active in queue74.6 GW423 requests
Agreement signed7,430 MW51 requests
Withdrawn670115.3 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

423 requests ยท page 1 of 9
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project J955, Sangamon County
Gas
1,165 MWUnder construction Sangamon, ILMISO Mar 2018target 2025
Heritage Prairie Wind
Onshore wind
850 MWAgreement signed Kankakee, ILPJM Sep 2017target 2028
Solar project J2186, Fulton County
Solar
821 MWIn study Fulton, ILMISO Jun 2022target 2024
Coal project IP17, Franklin County
Coal
550 MWAgreement signed Franklin, ILMISO Dec 2001target 2002
Other project J2694, Christian County
Other
500 MWIn study Christian, ILMISO Sep 2022target 2027
Solar + storage project J3076, Wabash County
Solar + storage
500 MWIn study Wabash, ILMISO Sep 2022target 2025
Wind + storage project J2690, Washington County
Wind + storage
500 MWIn study Washington, ILMISO Sep 2022target 2027
Onshore wind project J3860, Peoria County
Onshore wind
500 MWIn study Peoria, ILMISO Jan 2025target 2030
Other project J2171, Perry County
Other
500 MWIn study Perry, ILMISO Mar 2022target 2024
Battery storage project AH2-416, Livingston County
Battery storage
450 MWIn study Livingston, ILPJM Mar 2022target 2026
Onshore wind project J3730, Macoupin County
Onshore wind
444 MWIn study Macoupin, ILMISO Apr 2024target 2028
Solar + storage project J1263, Clark County
Solar + storage
409 MWAgreement signed Clark, ILMISO Apr 2019target 2025
Onshore wind project J3712, Peoria County
Onshore wind
400 MWIn study Peoria, ILMISO Apr 2024target 2028
Wind + storage project J3015, Iroquois County
Wind + storage
400 MWIn study Iroquois, ILMISO Sep 2022target 2027
Surplus; G876/G877
Wind + storage
400 MWIn study Mclean, ILMISO Sep 2022target 2025
Battery storage project AG2-545, Mchenry County
Battery storage ยท Monarch Grid, LLC
400 MWIn study Mchenry, ILPJM Mar 2025target 2024
Surplus; Glacier Moraine
Other
360 MWIn study Cumberland, ILMISO Jul 2024target 2027
Battery storage project AJ1-012, Lake County
Battery storage
354 MWIn study Lake, ILPJM May 2023target 2027
Solar + storage project J2390, Fulton County
Solar + storage
350 MWIn study Fulton, ILMISO Sep 2022target 2026
Onshore wind project J3521, Shelby County
Onshore wind
350 MWIn study Shelby, ILMISO Apr 2024target 2028
Solar project AH2-340, Stark County
Solar
350 MWIn study Stark, ILPJM Mar 2022target 2027
Panther Grove Wind
Onshore wind
350 MWAgreement signed Woodford, ILPJM Sep 2018target 2027
Solar project J4000, Scott County
Solar
343 MWIn study Scott, ILMISO Apr 2025target 2030
Gas project J1839, Macon County
Gas
340 MWIn study Macon, ILMISO Jun 2020target 2026
Solar project J3950, Clark County
Solar
340 MWIn study Clark, ILMISO Feb 2025target 2030
Onshore wind project J3991, Mclean County
Onshore wind
340 MWIn study Mclean, ILMISO Apr 2025target 2029
Battery storage project AJ1-011, Lake County
Battery storage
328 MWIn study Lake, ILPJM May 2023target 2027
Replacing 106 MW Coal with 106 MW BESS; Edwards Unit 3
Other
322 MWIn study Peoria, ILMISO Jul 2024target 2025
Solar project J2603, Mason County
Solar
320 MWIn study Mason, ILMISO Sep 2022target 2026
Pleasant Grove Solar
Solar ยท Deriva Energy Solar, LLC
300 MWIn study Mchenry, ILPJM Mar 2020target 2023
Onshore wind project J844, Knox County
Onshore wind
300 MWUnder construction Knox, ILMISO Jun 2017target 2021
Solar project J3498, Knox County
Solar
300 MWIn study Knox, ILMISO Apr 2024target 2028
Onshore wind project AH2-270, Whiteside County
Onshore wind
300 MWIn study Whiteside, ILPJM Mar 2022target 2026
Battery storage project J3946, Tazewell County
Battery storage
300 MWIn study Tazewell, ILMISO Mar 2025target 2030
Onshore wind project J3699, Henry County
Onshore wind
300 MWIn study Henry, ILMISO Apr 2024target 2028
Onshore wind project J3901, Shelby County
Onshore wind
300 MWIn study Shelby, ILMISO Jan 2025target 2030
Onshore wind project J1360, Piatt County
Onshore wind
300 MWAgreement signed Piatt, ILMISO Apr 2019target 2024
Battery storage project AI1-024, Mclean County
Battery storage
300 MWIn study Mclean, ILPJM Apr 2022target 2026
Onshore wind project J3681, Mclean County
Onshore wind
300 MWIn study Mclean, ILMISO Apr 2024target 2028
Solar project J1712, Perry County
Solar
300 MWIn study Perry, ILMISO Jun 2020target 2025
Battery storage project J2377, Peoria County
Battery storage
300 MWIn study Peoria, ILMISO Nov 2024target 2028
Wind + storage project J2128, Coles County
Wind + storage
300 MWIn study Coles, ILMISO Aug 2021target 2026
Steward Creek Solar
Solar ยท Steward Creek Solar, LLC
300 MWIn study Lee, ILPJM Dec 2019target 2023
Battery storage project J2647, Franklin County
Battery storage
300 MWIn study Franklin, ILMISO Sep 2022target 2028
Panther Grove 2
Onshore wind
300 MWAgreement signed Woodford, ILPJM Sep 2018target 2028
Dawson Solar
Solar ยท Deriva Energy Solar, LLC
300 MWIn study Mclean, ILPJM Sep 2020target 2024
Solar project J2556, Whiteside County
Solar
300 MWIn study Whiteside, ILMISO Sep 2022target 2026
Solar project J3412, Ford County
Solar
300 MWIn study Ford, ILMISO Mar 2024target 2028
Battery storage project AH2-415, Livingston County
Battery storage
300 MWIn study Livingston, ILPJM Mar 2022target 2026
Battery storage project J3558, Champaign County
Battery storage
300 MWIn study Champaign, ILMISO Apr 2024target 2027
Page 1 of 9

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)