United States › Grid › Interconnection queues › Illinois
ONSHORE WIND · MISOOnshore wind project J844, Knox County
Onshore wind project J844, Knox County is a 300 MW onshore wind request under construction in the MISO interconnection queue, in Knox County, Illinois, connecting to AMEREN TRANSMISSION COMPANY OF ILLINOIS.
Queue statusUnder construction
- PlanningQueued Jun 2017 (completed)
- ConsentedDec 2019 (completed)
- Construction (current stage)
- OperatingTarget May 2021 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- J844
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMEREN TRANSMISSION COMPANY OF ILLINOIS
- Connection point (POI)
- Sandburg Substation 138kV Bus
- Location
- Knox County, Illinois
- Technology
- Wind: 300 MW
- Total requested
- 300 MW
- Service type
- Energy only (ERIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Under Construction
- Queue status
- Active
- Entered queue
- 16 June 2017
- Agreement signed
- 10 December 2019
- Proposed online date
- May 2021
Location
Marker shows the centre of Knox County; the queue data does not give exact sites.
Other requests in Knox County
- Solar project J3498, Knox CountySolar · 300 MW · in study
- Onshore wind project J2938, Knox CountyOnshore wind · 200 MW · in study
- Battery storage project J3344, Knox CountyBattery storage · 100 MW · in study
- Solar project J3323, Knox CountySolar · 200 MW · withdrawn
- Onshore wind project R29, Knox CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project J008, Knox CountyOnshore wind · 150 MW · withdrawn
- Solar project J3343, Knox CountySolar · 100 MW · withdrawn
- Onshore wind project J887, Knox CountyOnshore wind · 75.0 MW · withdrawn
- Onshore wind project G694, Knox CountyOnshore wind · 62.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem