GAS · MISOGas project J955, Sangamon County
Gas project J955, Sangamon County is a 1,165 MW gas request under construction in the MISO interconnection queue, in Sangamon County, Illinois, connecting to AMEREN TRANSMISSION COMPANY OF ILLINOIS.
Queue statusUnder construction
- PlanningQueued Mar 2018 (completed)
- ConsentedApr 2022 (completed)
- Construction (current stage)
- OperatingTarget Jan 2025 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- J955
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMEREN TRANSMISSION COMPANY OF ILLINOIS
- Connection point (POI)
- Austin Substation 345kV Bus
- Location
- Sangamon County, Illinois
- Technology
- Gas: 1,165 MW
- Total requested
- 1,165 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Under Construction
- Queue status
- Active
- Entered queue
- 8 March 2018
- Agreement signed
- 26 April 2022
- Proposed online date
- January 2025
Location
Marker shows the centre of Sangamon County; the queue data does not give exact sites.
Other requests in Sangamon County
- Solar project J3418, Sangamon CountySolar · 220 MW · in study
- Battery storage project J2532, Sangamon CountyBattery storage · 200 MW · in study
- Battery storage project J3515, Sangamon CountyBattery storage · 200 MW · in study
- Solar project J2659, Sangamon CountySolar · 150 MW · in study
- Lincoln Capital Land LLC Solar ProjectSolar · 128 MW · in study
- Solar + storage project J2886, Sangamon CountySolar + storage · 115 MW · in study
- Solar project J1610, Sangamon CountySolar · 100 MW · in study
- Solar + storage project J2474, Sangamon CountySolar + storage · 100 MW · in study
- Battery storage project J3892, Sangamon CountyBattery storage · 50.0 MW · in study
- Coal project G412, Sangamon CountyCoal · 200 MW · built
- Onshore wind project J038, Sangamon CountyOnshore wind · 498 MW · withdrawn
- Wind + storage project J2039, Sangamon CountyWind + storage · 400 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem