United States › Grid › Interconnection queues › Illinois
SOLAR + STORAGE · MISOSolar + storage project J2886, Sangamon County
Solar + storage project J2886, Sangamon County is a 115 MW solar + storage request in interconnection study in the MISO interconnection queue, in Sangamon County, Illinois, connecting to AMEREN ILLINOIS.
- PlanningQueued Sep 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Nov 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J2886
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMEREN ILLINOIS
- Connection point (POI)
- 4Auburn N-4Jacksnvl 138kV
- Location
- Sangamon County, Illinois
- Technology
- Solar: 115 MW · Battery
- Total requested
- 115 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 15 September 2022
- Proposed online date
- November 2026
Location
Marker shows the centre of Sangamon County; the queue data does not give exact sites.
Other requests in Sangamon County
- Gas project J955, Sangamon CountyGas · 1,165 MW · under construction
- Solar project J3418, Sangamon CountySolar · 220 MW · in study
- Battery storage project J2532, Sangamon CountyBattery storage · 200 MW · in study
- Battery storage project J3515, Sangamon CountyBattery storage · 200 MW · in study
- Solar project J2659, Sangamon CountySolar · 150 MW · in study
- Lincoln Capital Land LLC Solar ProjectSolar · 128 MW · in study
- Solar project J1610, Sangamon CountySolar · 100 MW · in study
- Solar + storage project J2474, Sangamon CountySolar + storage · 100 MW · in study
- Battery storage project J3892, Sangamon CountyBattery storage · 50.0 MW · in study
- Coal project G412, Sangamon CountyCoal · 200 MW · built
- Onshore wind project J038, Sangamon CountyOnshore wind · 498 MW · withdrawn
- Wind + storage project J2039, Sangamon CountyWind + storage · 400 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem