Lincoln Capital Land LLC Solar Project

Lincoln Capital Land LLC Solar Project is a 128 MW solar request in interconnection study in the MISO interconnection queue, in Sangamon County, Illinois, connecting to City Water Light & Power (CWLP).

Queue statusIn planning
  1. PlanningQueued Aug 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
E0003
Grid region
MISO (Midcontinent)
Utility / transmission owner
City Water Light & Power (CWLP)
Developer
Lincoln Capital Land LLC
Connection point (POI)
Palomino 138kV Substation
Location
Sangamon County, Illinois
Technology
Solar: 128 MW
Total requested
128 MW
Service type
Network resource (NRIS)
Study phase
Request Status: Active; Post GIA Status: Not started
Queue status
Active
Entered queue
6 August 2025
Proposed online date
June 2028

Location

Marker shows the centre of Sangamon County; the queue data does not give exact sites.

Power plants in Illinois · Transmission lines in Illinois

Other requests in Sangamon County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem