Interconnection queue in Vermont

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5129 MW
Active in queue129 MW5 requests
Agreement signed90.0 MW3 requests
Withdrawn602,202 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5 requests
ProjectCapacityStatusLocationRegionQueuedOnline
FPS Panton Solar
Solar
50.0 MWAgreement signed Addison, VTISO-NE Dec 2018target 2027
Fair Haven Solar
Solar
20.0 MWAgreement signed Rutland, VTISO-NE Aug 2017target 2027
Shaftsbury Solar
Solar
20.0 MWAgreement signed Bennington, VTISO-NE Jul 2017target 2028
Battery Storage
Battery storage
19.3 MWIn study Windsor, VTISO-NE Feb 2024target 2029
Battery Storage
Battery storage
19.3 MWIn study Franklin, VTISO-NE Mar 2024target 2029

Capacity in the queue by state

Click a state to drill down.

By grid region

ISO/RTO markets and the non-ISO West and Southeast.

Requests by year joined

Capacity of requests in this view, by the year they entered the queue. Click a year.

20172024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)