United States › Grid › Interconnection queues › Vermont
BATTERY STORAGE · ISO-NEBattery Storage
Battery Storage is a 19.3 MW battery storage request in interconnection study in the ISO-NE interconnection queue, in Franklin County, Vermont.
Queue statusIn planning
- PlanningQueued Mar 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jul 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 1502
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- Direct connection to VELCO 115kV Highgate substation (44.943833, -73.058515)
- Location
- Franklin County, Vermont
- Technology
- Battery: 19.3 MW
- Total requested
- 19.3 MW
- Service type
- Network resource (NRIS)
- Study phase
- In Progress (unknown study)
- Queue status
- Active
- Entered queue
- 28 March 2024
- Proposed online date
- July 2029
Location
Marker shows the centre of Franklin County; the queue data does not give exact sites.
Other requests in Franklin County
- VPPSA Swanton Gas Turbine #1Gas · 21.0 MW · built
- SolarSolar · 196 MW · withdrawn
- SolarSolar · 20.1 MW · withdrawn
- SolarSolar · 20.1 MW · withdrawn
- solarSolar · 20.0 MW · withdrawn
- SolarSolar · 20.0 MW · withdrawn
- SolarSolar · 20.0 MW · withdrawn
- windOnshore wind · 20.0 MW · withdrawn
- SolarSolar · 20.0 MW · withdrawn
- SolarSolar · 19.9 MW · withdrawn
- SolarSolar · 19.9 MW · withdrawn
- windOnshore wind · 17.4 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem