πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Vermont

ONSHORE WIND Β· ISO-NE

wind

wind is a 17.4 MW onshore wind request withdrawn in the ISO-NE interconnection queue, in Franklin County, Vermont.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2015 (completed)
  2. Withdrawn / abandonedJun 2016 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
532
Grid region
ISO-NE (New England)
Connection point (POI)
GMP 34.5 kV Line between North St. Albans and Sheldon Springs Substations. State Route 105, Swanton, Vermont
Location
Franklin County, Vermont
Technology
Wind: 17.4 MW
Total requested
17.4 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
27 February 2015
Proposed online date
September 2016
Withdrawn
June 2016

Location

Marker shows the centre of Franklin County; the queue data does not give exact sites.

Power plants in Vermont Β· Transmission lines in Vermont

Other requests in Franklin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem