GAS · ISO-NEVPPSA Swanton Gas Turbine #1
VPPSA Swanton Gas Turbine #1 is a 21.0 MW gas request built and operating in the ISO-NE interconnection queue, in Franklin County, Vermont.
Request details
- Queue ID
- 224
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- Swanson Village 46 kV System
- Location
- Franklin County, Vermont
- Technology
- Gas: 21.0 MW · Oil
- Total requested
- 21.0 MW
- Study phase
- IA Executed
- Queue status
- Operational
- Entered queue
- 10 August 2007
- Proposed online date
- February 2010
Location
Marker shows the centre of Franklin County; the queue data does not give exact sites.
Other requests in Franklin County
- Battery StorageBattery storage · 19.3 MW · in study
- SolarSolar · 196 MW · withdrawn
- SolarSolar · 20.1 MW · withdrawn
- SolarSolar · 20.1 MW · withdrawn
- solarSolar · 20.0 MW · withdrawn
- SolarSolar · 20.0 MW · withdrawn
- SolarSolar · 20.0 MW · withdrawn
- windOnshore wind · 20.0 MW · withdrawn
- SolarSolar · 20.0 MW · withdrawn
- SolarSolar · 19.9 MW · withdrawn
- SolarSolar · 19.9 MW · withdrawn
- windOnshore wind · 17.4 MW · withdrawn