Requests shown30059.6 GW
Active in queue59.6 GW300 requests
Agreement signed11.2 GW69 requests
Withdrawn579114.4 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

300 requests ยท page 1 of 6
ProjectCapacityStatusLocationRegionQueuedOnline
Schahfer CCGTs
Gas ยท NIPSCO
2,740 MWIn study Jasper, INMISO Aug 2025target 2028
Gas project J3999, Vermillion County
Gas
1,540 MWIn study Vermillion, INMISO Apr 2025target 2030
Malden CCGT
Gas ยท NIPSCO
1,090 MWIn study Porter, INMISO Aug 2025target 2028
Replacing 1014.7 MW of coal generation with Gas/Steam; Cayuga CC1 CC2
Gas
1,040 MWIn study Vermillion, INMISO Feb 2024target 2028
Replacing 722 MW Coal with 285 MW of Battery and 437MW of Gas; Schahfer
Gas
733 MWIn study Jasper, INMISO Dec 2024target 2027
Gas project J351, St. Joseph County
Gas
715 MWAgreement signed St. Joseph, INMISO May 2014target 2020
Gas project AG2-072, Spencer County
Gas ยท Bluegrass Power LLC
700 MWIn study Spencer, INPJM Feb 2025target 2026
Solar project AH2-348, Daviess County
Solar
700 MWIn study Daviess, INPJM Mar 2022target 2025
Solar project J2846, Pulaski County
Solar
700 MWIn study Pulaski, INMISO Sep 2022target 2025
Gas project J3604, Sullivan County
Gas
650 MWIn study Sullivan, INMISO Apr 2024target 2027
Gas project J3084, Sullivan County
Gas
642 MWIn study Sullivan, INMISO Aug 2025target 2026
Malden BESS
Battery storage ยท NIPSCO
630 MWIn study Porter, INMISO Aug 2025target 2027
Sullivan Generating Station 1
Gas
575 MWAgreement signed Sullivan, INPJM Oct 2015target 2027
Sullivan Generating Station 2
Gas
575 MWAgreement signed Sullivan, INPJM Oct 2015target 2027
Solar + storage project J3075, Sullivan County
Solar + storage
560 MWIn study Sullivan, INMISO Sep 2022target 2025
Merom Station
Gas ยท Hallador Power
530 MWIn study Sullivan, INMISO Nov 2025target 2028
Mitchell BESS
Battery storage ยท NIPSCO
527 MWIn study Lake, INMISO Aug 2025target 2028
Solar project J3931, Jasper County
Solar
500 MWIn study Jasper, INMISO Feb 2025target 2030
Gas project J3232, Vermillion County
Gas
500 MWIn study Vermillion, INMISO Apr 2024target 2028
Gas project J4005, Sullivan County
Gas
500 MWIn study Sullivan, INMISO May 2025target 2028
Solar + storage project LGE-GIS-2021-008, Clark County
Solar + storage
500 MWPaused / redesign Clark, INSoutheast Mar 2021target 2026
Gas project J4021, Sullivan County
Gas
470 MWIn study Sullivan, INMISO May 2025target 2028
Gas project J3331, Sullivan County
Gas
470 MWIn study Sullivan, INMISO Apr 2024target 2028
Dolphin Solar
Solar ยท Dolphin Solar LLC
450 MWIn study Fountain, INPJM Sep 2020target 2024
Battery storage project AI1-022, Huntington County
Battery storage
450 MWIn study Huntington, INPJM Apr 2022target 2026
Merom Storage
Solar + storage ยท Hoosier Energy / Solvenz
405 MWIn study Sullivan, INMISO Dec 2025target 2028
Battery storage project J2496, White County
Battery storage
400 MWIn study White, INMISO Sep 2022target 2026
Solar project AH2-352
Solar
400 MWIn study INPJM Mar 2022target 2026
Solar project AH2-257, Vermillion County
Solar
400 MWIn study Vermillion, INPJM Mar 2022target 2024
Gas project J3666, Morgan County
Gas
379 MWIn study Morgan, INMISO Apr 2024target 2028
Solar project J3942, Vigo County
Solar
365 MWIn study Vigo, INMISO Feb 2025target 2030
Solar + storage project AH2-413, Huntington County
Solar + storage
365 MWIn study Huntington, INPJM Mar 2022target 2026
Battery storage project AH2-414, Huntington County
Battery storage
350 MWIn study Huntington, INPJM Mar 2022target 2026
Solar project J3943, Vigo County
Solar
337 MWIn study Vigo, INMISO Feb 2025target 2030
Brickyard Energy Storage
Battery storage ยท Brickyard Energy Storge, LLC
310 MWIn study Boone, INMISO Aug 2025target 2028
Mammoth South Energy Center
Solar
300 MWAgreement signed Pulaski, INPJM Mar 2020target 2027
Mammoth Central Energy Center
Solar
300 MWAgreement signed Pulaski, INPJM Mar 2020target 2027
Battery storage project J2215, Lake County
Battery storage
300 MWIn study Lake, INMISO Mar 2022target 2024
Solar + storage project J3114, Greene County
Solar + storage
300 MWIn study Greene, INMISO Nov 2025target 2026
Mammoth Central II Energy Center
Solar
300 MWAgreement signed Pulaski, INPJM Sep 2020target 2028
Solar project J1058, Lake County
Solar
300 MWUnder construction Lake, INMISO Mar 2018target 2024
Onshore wind project J3910, Newton County
Onshore wind
300 MWIn study Newton, INMISO Feb 2025target 2030
Solar project J2270, Sullivan County
Solar
300 MWIn study Sullivan, INMISO Aug 2021target 2024
Battery storage project J3834, Gibson County
Battery storage
300 MWIn study Gibson, INMISO Sep 2024target 2026
Solar project J1308, Posey County
Solar
300 MWAgreement signed Posey, INMISO Apr 2019target 2024
Onshore wind project J4063, Knox County
Onshore wind
300 MWIn study Knox, INMISO Sep 2025target 2030
Solar project J1743, Miami County
Solar
293 MWIn study Miami, INMISO Apr 2022target 2026
Solar project AI1-085, Wayne County
Solar
290 MWIn study Wayne, INPJM Jul 2022target 2030
Sandcut Storage
Solar + storage ยท Hoosier Energy / Solvenz
280 MWIn study Vigo, INMISO Dec 2025target 2028
Onshore wind project J3564, Newton County
Onshore wind
275 MWIn study Newton, INMISO Apr 2024target 2028
Page 1 of 6

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)