Solar project AH2-348, Daviess County

Solar project AH2-348, Daviess County is a 700 MW solar request in interconnection study in the PJM interconnection queue, in Daviess County, Indiana, connecting to AEP.

Queue statusIn planning
  1. PlanningQueued Mar 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AH2-348
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Jefferson - Rockport 765 kV
Location
Daviess County, Indiana
Technology
Solar: 700 MW
Total requested
700 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Active
Entered queue
10 March 2022
Proposed online date
December 2025

Location

Marker shows the centre of Daviess County; the queue data does not give exact sites.

Power plants in Indiana · Transmission lines in Indiana

Other requests in Daviess County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem