SOLAR + STORAGE Β· MISO

Solar + storage project J3094, Daviess County

Solar + storage project J3094, Daviess County is a 115 MW solar + storage request withdrawn in the MISO interconnection queue, in Daviess County, Indiana, connecting to DUKE ENERGY INDIANA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedOct 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J3094
Grid region
MISO (Midcontinent)
Utility / transmission owner
DUKE ENERGY INDIANA
Connection point (POI)
Pumpkin Center 230kV
Location
Daviess County, Indiana
Technology
Solar: 115 MW Β· Battery
Total requested
115 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
15 September 2022
Proposed online date
September 2026
Withdrawn
October 2025

Location

Marker shows the centre of Daviess County; the queue data does not give exact sites.

Power plants in Indiana Β· Transmission lines in Indiana

Other requests in Daviess County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem