🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Indiana

SOLAR · MISO

Solar project J3942, Vigo County

Solar project J3942, Vigo County is a 365 MW solar request in interconnection study in the MISO interconnection queue, in Vigo County, Indiana, connecting to DUKE ENERGY INDIANA.

Queue statusIn planning
  1. PlanningQueued Feb 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2030 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J3942
Grid region
MISO (Midcontinent)
Utility / transmission owner
DUKE ENERGY INDIANA
Connection point (POI)
Sandford
Location
Vigo County, Indiana
Technology
Solar: 365 MW
Total requested
365 MW
Service type
Network resource (NRIS)
Queue status
Active
Entered queue
20 February 2025
Proposed online date
June 2030

Location

Marker shows the centre of Vigo County; the queue data does not give exact sites.

Power plants in Indiana · Transmission lines in Indiana

Other requests in Vigo County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem