United States › Grid › Interconnection queues › Indiana
COAL · MISOCoal project J333, Vigo County
Coal project J333, Vigo County is a 170 MW coal request built and operating in the MISO interconnection queue, in Vigo County, Indiana.
Request details
- Queue ID
- J333
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Wabash River 230 kV Bus
- Location
- Vigo County, Indiana
- Technology
- Coal: 170 MW
- Total requested
- 170 MW
- Study phase
- DPP - SIS
- Queue status
- Operational
- Entered queue
- 16 May 2014
- Agreement signed
- 20 November 2014
- Proposed online date
- December 2010
- Came online
- December 2010
Location
Marker shows the centre of Vigo County; the queue data does not give exact sites.
Other requests in Vigo County
- Solar project J3942, Vigo CountySolar · 365 MW · in study
- Solar project J3943, Vigo CountySolar · 337 MW · in study
- Sandcut StorageSolar + storage · 280 MW · in study
- Solar project J1721, Vigo CountySolar · 175 MW · in study
- Solar project J3724, Vigo CountySolar · 132 MW · in study
- Solar + storage project J2301, Vigo CountySolar + storage · 100 MW · in study
- Gas project J3870, Vigo CountyGas · 87.0 MW · in study
- Solar project J4034, Vigo CountySolar · 70.0 MW · in study
- Gas project G780, Vigo CountyGas · 578 MW · built
- Gas project G010, Vigo CountyGas · 500 MW · built
- Coal project J334, Vigo CountyCoal · 180 MW · built
- Gas project J542, Vigo CountyGas · 1,235 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem