Solar project J3724, Vigo County

Solar project J3724, Vigo County is a 132 MW solar request in interconnection study in the MISO interconnection queue, in Vigo County, Indiana, connecting to DUKE ENERGY INDIANA.

Queue statusIn planning
  1. PlanningQueued Apr 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J3724
Grid region
MISO (Midcontinent)
Utility / transmission owner
DUKE ENERGY INDIANA
Connection point (POI)
Sandford
Location
Vigo County, Indiana
Technology
Solar: 132 MW
Total requested
132 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Active
Entered queue
16 April 2024
Proposed online date
September 2028

Location

Marker shows the centre of Vigo County; the queue data does not give exact sites.

Power plants in Indiana · Transmission lines in Indiana

Other requests in Vigo County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem