BATTERY STORAGE · MISO

Mitchell BESS

Mitchell BESS is a 527 MW battery storage request in interconnection study in the MISO interconnection queue, in Lake County, Indiana, connecting to NIPSCO.

Queue statusIn planning
  1. PlanningQueued Aug 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
E0033
Grid region
MISO (Midcontinent)
Utility / transmission owner
NIPSCO
Developer
NIPSCO
Connection point (POI)
Mitchell Gen. Station
Location
Lake County, Indiana
Technology
Battery: 527 MW
Total requested
527 MW
Service type
Network resource (NRIS)
Study phase
Request Status: Active; Post GIA Status: Not started
Queue status
Active
Entered queue
6 August 2025
Proposed online date
August 2028

Location

Marker shows the centre of Lake County; the queue data does not give exact sites.

Power plants in Indiana · Transmission lines in Indiana

Other requests in Lake County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem