United States β€Ί Grid β€Ί Interconnection queues β€Ί Indiana

BATTERY STORAGE Β· PJM

Battery storage project AI2-023, Lake County

Battery storage project AI2-023, Lake County is a 200 MW battery storage request withdrawn in the PJM interconnection queue, in Lake County, Indiana, connecting to ComEd.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2022 (completed)
  2. Withdrawn / abandonedJan 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AI2-023
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ComEd
Connection point (POI)
Lake - 270888 345kV
Location
Lake County, Indiana
Technology
Battery: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
20 December 2022
Proposed online date
December 2028
Withdrawn
January 2025

Location

Marker shows the centre of Lake County; the queue data does not give exact sites.

Power plants in Indiana Β· Transmission lines in Indiana

Other requests in Lake County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem