United States βΊ Grid βΊ Interconnection queues βΊ Indiana
BATTERY STORAGE Β· PJMBattery storage project AI2-023, Lake County
Battery storage project AI2-023, Lake County is a 200 MW battery storage request withdrawn in the PJM interconnection queue, in Lake County, Indiana, connecting to ComEd.
Queue statusWithdrawn / abandoned
- PlanningQueued Dec 2022 (completed)
- Withdrawn / abandonedJan 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AI2-023
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- ComEd
- Connection point (POI)
- Lake - 270888 345kV
- Location
- Lake County, Indiana
- Technology
- Battery: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 20 December 2022
- Proposed online date
- December 2028
- Withdrawn
- January 2025
Location
Marker shows the centre of Lake County; the queue data does not give exact sites.
Other requests in Lake County
- Solar project J1058, Lake CountySolar Β· 300 MW Β· under construction
- Bottlebrush SolarSolar Β· 200 MW Β· agreement signed
- Solar project J1386, Lake CountySolar Β· 100 MW Β· agreement signed
- Mitchell BESSBattery storage Β· 527 MW Β· in study
- Battery storage project J2215, Lake CountyBattery storage Β· 300 MW Β· in study
- Replacing 100 MW of Solar with storage; J1386Battery storage Β· 100 MW Β· in study
- Surplus; J1386Other Β· 50.0 MW Β· in study
- Surplus; J1386Other Β· 50.0 MW Β· in study
- Gas project Y3-063, Lake CountyGas Β· 1,161 MW Β· withdrawn
- Coal project G758, Lake CountyCoal Β· 550 MW Β· withdrawn
- Battery storage project J1353, Lake CountyBattery storage Β· 150 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem