SOLAR · PJMMammoth South Energy Center
Mammoth South Energy Center is a 300 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Pulaski County, Indiana, connecting to AEP.
Queue statusConsented
- PlanningQueued Mar 2020 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Feb 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- AF2-133
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Reynolds-Olive #2 345 kV
- Location
- Pulaski County, Indiana
- Technology
- Solar: 300 MW
- Total requested
- 300 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Active
- Entered queue
- 4 March 2020
- Proposed online date
- February 2027
Location
Marker shows the centre of Pulaski County; the queue data does not give exact sites.
Other requests in Pulaski County
- Mammoth Central Energy CenterSolar · 300 MW · agreement signed
- Mammoth Central II Energy CenterSolar · 300 MW · agreement signed
- Mayapple SolarSolar · 260 MW · agreement signed
- Moss Creek SolarSolar · 200 MW · agreement signed
- Solar project J2846, Pulaski CountySolar · 700 MW · in study
- Solar project J2849, Pulaski CountySolar · 245 MW · in study
- Battery storage project AH2-233, Pulaski CountyBattery storage · 100 MW · in study
- Battery storage project AH1-482, Pulaski CountyBattery storage · 78.0 MW · in study
- Battery storage project AH1-302, Pulaski CountyBattery storage · 75.0 MW · in study
- Solar + storage project J3119, Pulaski CountySolar + storage · 350 MW · withdrawn
- Solar project AF2-190, Pulaski CountySolar · 260 MW · withdrawn
- Solar project J1726, Pulaski CountySolar · 200 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem