United States › Grid › Interconnection queues › Indiana

BATTERY STORAGE · PJM

Battery storage project AH1-482, Pulaski County

Battery storage project AH1-482, Pulaski County is a 78.0 MW battery storage request in interconnection study in the PJM interconnection queue, in Pulaski County, Indiana, connecting to AEP.

Queue statusIn planning
  1. PlanningQueued Feb 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2023 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AH1-482
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Developer
Lightsource Renewable Energy Development, LLC
Connection point (POI)
Olive - Reynolds #2 345 kV
Location
Pulaski County, Indiana
Technology
Battery: 78.0 MW
Total requested
78.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Active
Entered queue
25 February 2025
Proposed online date
September 2023

Location

Marker shows the centre of Pulaski County; the queue data does not give exact sites.

Power plants in Indiana · Transmission lines in Indiana

Other requests in Pulaski County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem