SOLAR · PJM

Mayapple Solar

Mayapple Solar is a 260 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Pulaski County, Indiana, connecting to AEP.

Queue statusConsented
  1. PlanningQueued Sep 2020 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
AG1-349
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Olive-Reynolds #2 345 kV
Location
Pulaski County, Indiana
Technology
Solar: 260 MW
Total requested
260 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Active
Entered queue
30 September 2020
Proposed online date
December 2027

Location

Marker shows the centre of Pulaski County; the queue data does not give exact sites.

Power plants in Indiana · Transmission lines in Indiana

Other requests in Pulaski County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem